Line delivery

How to Compare Block Plant Quotations Line by Line

Two quotations describe two different plants. Convert both to cost per saleable block at one stated block, load every exclusion at your own local cost, then compare.

QUICK ANSWER

Compare block plant quotations by converting both to cost per saleable block at one stated block size, mix, shift length and curing method. Load every excluded item at your own local cost, including pallets, extra moulds, power connection, civil works and unloading. Then divide the loaded total by the output per shift that the acceptance test will measure. Comparing quotation totals ranks the paperwork, not the plants, and it usually produces the wrong decision.

What should a block plant quotation be compared on?

Two quotations for a block plant are almost never comparable as they arrive, because each one prices a different plant. One includes three moulds, a pallet feeder and a curing system. The other includes one mould and a host. Comparing the totals tells you which is cheaper. Comparing the scopes tells you which one builds the plant you asked for.

The comparison has to be made on a single unit that both offers can be converted to. The only unit that survives the conversion is the cost per saleable block, at a stated block type, mix, shift length and curing method, with every exclusion counted as a cost the buyer will pay separately.

Comparison lineWhy it decides the answer
Host model and forming cycleSets moulds per hour before anything else is counted
Pallet size and blocks per mouldConverts a machine into an output figure
Installed power of every itemSets the transformer and the cable, ordered months ahead
Mould packageOne mould means one product, and buyers usually need three
Pallet fleetWith 24 hour curing, the fleet caps daily output
Batching, mixing and feedingOften quoted separately, always needed
Cubing, wrapping, strappingSells the block as a stack, not as a loose piece
Spare kitThe difference between a week and a month of downtime
Training and commissioningNamed days, named engineer, or it is settled on site
Acceptance testsThe only written proof of output before the balance is paid
Warranty start dateAcceptance or shipment, and the difference is months
ExclusionsCivil works, power connection, unloading, foundations

How do you put two quotations on the same output basis?

Start with the pallet, not the host. Every model in this range works to a different tray, and the tray decides how many blocks leave the machine per cycle.

HostPallet sizeInstalled powerWeightForming cycle
QST6-15980 x 680 x 20 mm34.4 kW12 t15 to 23 s
QST8-15980 x 860 x 22 mm44.9 kW14 t15 to 23 s
QST12001350 x 880 x 25 mm57.6 kW17 tconfirm from drawing
QST15001350 x 1150 x 30 mm69.1 kW20 tconfirm from drawing

The QST6-15 makes six hollow blocks of 390 x 190 x 190 mm per mould and is rated at 8,640 to 11,520 per eight hour shift. A host on a 1350 x 1150 mm tray makes a different count per cycle, so a lower price on the machine can still be a higher cost per block. Never compare the two prices directly. Convert both to blocks per shift at the same block size, then divide.

Where a specification sheet does not state a forming cycle, the QST1200 and QST1500 sheets are honest about this, take the cycle from the general arrangement drawing of the machine being offered. A cycle time invented for a comparison table is worse than a blank cell.

Which items are usually missing from the cheaper quotation?

The gap between two offers is rarely in the host. It is almost always in the scope around it.

Moulds beyond the first. A quotation normally names one mould. A plant selling hollow blocks, solid blocks and pavers needs one mould per shape and size, and each is a separately priced item.

The pallet fleet. Pallets are sometimes quoted per piece and sometimes left to the buyer. A line with no pallet fleet cannot run a single shift, so this is not an optional line.

The pallet feeder. A QS-1200 feeder holds three stacks, weighs about 1,300 kg, draws 3 kW and cycles in roughly 13 seconds. Without it the host waits for pallets, and the shortfall appears as a machine that never reaches its rating.

Batching and mixing. A batching machine with two to four hoppers, three point weighing and dual speed discharge, plus a planetary or twin shaft mixer sized to the host cycle, is part of the plant even when it is quoted by a different supplier.

Cubing and packing. A palletizer such as the QS-1200A draws 29.5 kW, handles stacks up to 1200 x 1200 x 1400 mm on an 18 second layer cycle and weighs about 11,000 kg. The wrapper handles pack heights from 680 to 1,150 mm. A plant that sells loose blocks by the truckload needs neither. A plant selling to distributors needs both.

The spare kit. One full mould set, a pallet buffer, a hydraulic service kit, sensors, limit switches, one PLC module and exciter bearings.

Training days and the commissioning engineer. A number of days, a named engineer and who pays the flights and the hotel. Left out, this becomes an invoice after arrival.

Documents. Foundation and anchor drawings, electrical drawings, the PLC programme backup, and a manual in the language the crew reads.

Why does installed power belong in the comparison?

Because it is the largest item the buyer pays for that is not in the quotation. The installed load of the line sets the transformer size, the incoming cable and the protective panel, and those are ordered and installed before the machines arrive.

A compact host at 34.4 kW and a large host at 104 kW do not differ by 70 kW on the utility application, they differ by the whole plant behind them: mixer, batching, pallet feeder, palletizer, wrapper, compressors and lighting. Two offers that look close on machine price can be far apart on the power connection, which is a local cost the buyer carries alone.

The comparison line should be the total installed load of every item in the offer, added up and written on one row. If a supplier cannot state it, the offer is not yet a plant specification.

How should automation level be scored rather than priced?

Automation is not a feature to be priced, it is a crew size to be costed. A high level automatic line in the QSGW range runs 30,000 to 250,000 pieces per eight hour shift with three to six persons per shift. A semi automatic plant producing a fraction of that can still carry a larger crew, because pallets are moved by hand and blocks are stacked by hand.

The comparison should put three figures side by side for each offer: capital cost, crew per shift, and output per shift at the agreed block. The cheaper capital figure frequently loses on the other two once wages are counted over several years, and the more expensive one frequently loses if the plant will run a single shift for its first two years.

What belongs in the acceptance and warranty lines?

These two lines decide whether the plant can prove anything after the last container is opened, and they are the most commonly left vague.

The acceptance line should name the tests: a cold run of every motion, at least ten consecutive automatic cycles without a manual intervention, hydraulic pressure held at the rated value, 25 MPa on a QST6-15, 31.5 MPa on a QST8-15 and across the QS static press range, vibration frequency inside its band of 3,800 to 4,500 cycles per minute, and a full shift count of finished blocks at the agreed size. It should also say who signs, what is recorded, and that samples are retained.

The warranty line should state its start date. If it starts at the bill of lading, the ocean transit and the weeks in the yard are paid for out of the buyer's cover. If it starts at the signed acceptance, the buyer gets the full period on a working plant.

An offer that mentions both in one sentence without a test list or a start date has not answered the question, and the answer will be negotiated on site, at the buyer's cost.

How do you compare delivery scope and shipping?

Ask for the container count and the loading plan, then check what is in the first container. A 40HQ gives roughly 2,350 mm of interior width and 2,690 mm of interior height, and a QST1500 host is 11,500 x 4,500 x 2,800 mm at 20 t, so a line ships as numbered sections rather than as a machine.

The first container should carry the items needed to start foundation work and the first assembly: anchor bolts, base plates, the first mould, the electrical cabinet and the drawings. A plan that puts them in the last container adds weeks to the schedule for no reason.

Delivery scope also has to say where the supplier's responsibility ends. Free on board, cost and freight, delivered to site, or delivered and unloaded are four different prices for the same equipment, and unloading a 20 t host without the right crane is a cost the buyer discovers on arrival.

What does the final comparison sheet look like?

One page, one row per scope item, one column per offer, and a total only at the bottom. The rows should be the ones in the first table on this page, with the buyer's own cost written in for every item the offer excludes.

Then three figures at the foot of the sheet: total cost including the buyer's exclusions, output per shift at the agreed block, and crew per shift. Divide the first by the second, multiply by the crew cost, and the offers can finally be ranked on the same basis.

That ranking is the only comparison that means anything, and it is usually different from the ranking by quotation total.

FAQ

Frequently Asked Questions

How do I compare two block plant quotations fairly?
Convert both to the same unit: cost per saleable block at one stated block size, mix, shift length and curing method. Add every excluded item at your own local cost, including pallets, extra moulds, the power connection, civil works and unloading. Then divide total cost by output per shift. Comparing quotation totals ranks the paperwork, not the plants.
Why can I not compare the price of two block machines directly?
Because each machine works to a different pallet, and the pallet decides how many blocks leave per cycle. A QST6-15 runs a 980 x 680 mm tray and makes six hollow blocks of 390 x 190 x 190 mm per mould. A host on a 1350 x 1150 mm tray makes a different count. Two prices on two trays describe two different outputs, so the cheaper machine can produce the more expensive block.
What is usually excluded from a block plant quotation?
Pallets beyond a sample, moulds beyond the first, the pallet feeder, batching and mixing, the palletizer and wrapper, the spare kit, the days of training, the commissioning engineer's travel and accommodation, unloading at site, civil works, the power connection, and a manual in the crew's language. Each exclusion is a cost the buyer pays, and none of them appears in the total being compared.
Should the comparison be done on price per block?
Yes, but only after the cost is fully loaded. Price per block on the quotation alone rewards the offer with the most exclusions. Load every excluded item, add the crew cost for the automation level offered, and divide by the output that the acceptance test will actually measure over a full shift, not by a figure extrapolated from a cycle time.
How do I compare automation levels between two offers?
Put capital cost, crew per shift and output per shift side by side for each offer. A high level automatic line in the QSGW range runs 30,000 to 250,000 pieces per eight hour shift with three to six persons. A semi automatic plant carrying a larger crew can still be cheaper to run if the plant works a single shift, and more expensive if it works three.
What documents should arrive with a block plant quotation?
The scope matrix, the equipment list with installed power for every item, block and mould drawings, the pallet size, the general arrangement drawing of the host, the foundation and anchor drawings, the electrical drawing, the loading plan with container allocation, and the acceptance test list. A quotation without a scope matrix cannot be compared with anything.
How should warranty and acceptance be compared between offers?
On the start date and on the test list. Warranty that starts at the bill of lading hands the transit and the yard time to the buyer; warranty that starts at signed acceptance gives the full period on a working plant. Acceptance should name the cold run, at least ten consecutive automatic cycles, rated hydraulic pressure and a full shift count of finished blocks.
How do I compare shipping and delivery scope?
Ask for the container count, the loading plan and the contents of the first container. Anchor bolts, base plates, the first mould, the electrical cabinet and the drawings should travel first, because foundation work cannot start without them. Then check whether the price is free on board, cost and freight, delivered to site, or delivered and unloaded, since those are four different prices.