Plant economics

Cost to Produce One Concrete Block: What Sets the Number

No supplier can publish a cost per block, because three of the four inputs are local. What can be fixed is the quantity of each input in one block, and that is what a plant can measure.

QUICK ANSWER

No plant can publish a universal cost per block, because cement price, aggregate price and the electricity tariff are local. What can be fixed is the quantity of each input inside one block. A 390 x 190 x 190 mm hollow block of about 15 kg contains roughly 1.4 to 1.6 kg of cement, about 13 kg of sand and aggregate, and up to 32 Wh of electricity at the nameplate ceiling of a QST6-15. Multiply those by your own prices, then add pallets, crew hours, rejects and a share of monthly fixed cost.

What does it cost to produce one concrete block?

There is no single figure, and a supplier who quotes one is quoting his own country's prices. The cost of one block is built from four measured quantities and one local price list: how much cement and aggregate the block contains, how much energy the line draws per thousand blocks, what the pallet fleet and the crew cost per thousand blocks, and what share of the plant's monthly fixed cost each block has to carry. Change the block size or the cement dosage and the first two quantities move. Change the shift pattern and the last two move.

This page deals with operating cost only. The capital side, meaning what the plant costs to build, is covered on the factory setup cost page and on the complete plant cost page. Keeping the two apart matters, because a machine payment is spread over years while a tonne of cement is paid for on delivery, and the two do not behave the same way when a plant runs below its plan.

Which quantities set the cost of one block?

Six lines cover almost the whole variable cost of a hollow block. Each one can be measured inside the plant on any working day, which is what makes a cost sheet worth keeping instead of copied from a brochure.

Cost lineMeasured per 1,000 hollow blocks, 390 x 190 x 190 mmWhere the figure comes from
Cement1.4 to 1.6 tonnesMix design at about 10 percent of a 15 kg block by weight
Sand and aggregateabout 13 tonnesThe balance of the same block weight, plus batching loss
Electricityup to 31.9 kWh34.4 kW installed, 8,640 blocks per shift, nameplate ceiling
Pallets167 mould loadsSix hollow blocks per mould, 1,440 pallets in circulation per shift
Labour5.6 to 7.4 crew hoursSix to eight crew for 8,640 blocks in eight hours
Rejects and reworkmeasured, four week recordThe plant's own counting sheet, added as a multiplier

Multiply each quantity by the price you actually pay and the sheet is complete. Cement is the line that moves the most, and not because the block contains much of it: at about 10 percent of the mass it is the smallest line by weight and usually the largest by cost, because aggregate is quarried nearby while cement arrives by bag or by bulk truck.

How much cement and aggregate does one block contain?

Start from block weight, not from a recipe copied from another plant. A 390 x 190 x 190 mm hollow block weighs roughly 14 to 16 kg when it leaves the machine, so a shift of 8,640 blocks is about 130 tonnes of finished product. With cement at about 10 percent of the mix by weight, that shift consumes around 13 tonnes of cement and close to 115 tonnes of sand and aggregate. Divide by the shift output and one block carries 1.4 to 1.6 kg of cement and about 13 kg of aggregate.

Dosage is a decision, not a constant. A block for a load bearing wall in an inspected project needs more cement than a partition block for a boundary wall, and the quality control page explains how to prove strength instead of assuming it. Every extra percent of cement on a 15 kg block adds 150 grams to each block and 1.5 tonnes to every 10,000 blocks, which is why the mix design belongs on the cost sheet and not only in the laboratory.

How much electricity does one block take?

Take the installed capacity of the host and divide it by the pieces it makes in a shift, and the result is a ceiling rather than a meter reading. On a QST6-15 with 34.4 kW installed, eight hours at full draw is 275.2 kWh, and at 8,640 hollow blocks that is 31.9 Wh per block. The same host on a standard brick mould reaches 3.8 to 4.0 Wh per piece, so a plant selling hollow blocks spends several times the energy per piece that a brick plant spends on the same machine.

The meter will read below that ceiling, because the hydraulic pump loads during the press stroke and the vibration motors run for a few seconds inside each cycle. Use the ceiling to size the transformer and the cable, and use four weeks of meter readings for the cost sheet. The gap between the two is often wide enough to change the answer on whether running a generator is worth the fuel.

What do pallets and labour add per block?

Pallets are capital, but they are consumed, so they belong in the cost per block as an amortised line. Count the mould loads: at six hollow blocks per mould, 1,000 blocks occupy 167 pallet loads, and a single shift line keeps 1,440 pallets in circulation. Divide the price of one pallet by the number of cycles it survives and by the blocks it carries in each cycle, and the cost per block appears. Two plants with the same host can differ by a factor of two on this line, because a plant that drops pallets at the stacker pays for them twice.

Labour follows the crew, not the machine rating. A QST6-15 line runs with six to eight people per shift, which is 48 to 64 crew hours for 8,640 blocks, or 5.6 to 7.4 hours per 1,000 blocks. Anything the plant does to raise output without adding people lowers this line directly, which is why automation pays back through labour and consistency rather than through machine speed alone.

How do rejects and downtime change the number?

Cost per block is usually calculated on blocks made, while the plant is paid on blocks sold. The difference is the reject pile, and the correction is one division: divide the cost per made block by one minus the reject rate. At a five percent reject rate every sold block carries 5.3 percent more cost than the sheet shows. At ten percent it carries 11 percent more, and at that level the reject pile can cost more than the cement saved by a leaner mix.

Downtime acts on the fixed side. A stopped line still pays rent, supervision and the machine instalment, so every lost shift raises the fixed cost carried by the blocks that were made. This is why a plant that writes down its stops usually finds two or three causes that are cheaper to remove than any change of mix or machine.

How do you find the break-even volume?

Divide the month's fixed cost by the margin on one block and the result is the number of blocks the plant must sell before it earns anything. Fixed cost here means land or rent, supervision and administration salaries, the machine instalment, insurance and the standing charge on the power connection. Variable cost is the six lines above, which stop when the plant stops.

The share of fixed cost carried by each block falls as volume rises. At 100,000 blocks a month each block carries one hundred thousandth of the month's fixed cost, and at 200,000 blocks it carries half of that. A plant selling 60,000 blocks a month from a line built for about 170,000 is not badly run, it is carrying a fixed cost per block that no mix change can rescue. Check that ratio before blaming the operator.

Why is a machine quotation not a cost per block?

Because the machine is one line of the capital budget and a small one in the running budget. Two plants can buy the same host and end up with different costs per block inside a year: one because its aggregate comes from another district, one because its cement arrives in bags instead of a silo, one because its pallet fleet cannot fill a second shift. None of those differences appears on a machine quotation.

Fill the cost sheet with your own numbers before comparing two suppliers. A supplier who cannot state the input quantities per 1,000 blocks, meaning cement, aggregate, energy and pallets, is quoting a machine rather than a plant.

Which five numbers belong on the plant's cost sheet?

Cement kilos per block, aggregate kilos per block, kilowatt hours per 1,000 blocks, pallet loads per 1,000 blocks and crew hours per 1,000 blocks. Add the reject rate and the month's fixed cost and the sheet is complete. Five numbers that a clerk can fill from the batch record, the meter, the pallet count and the attendance sheet, with no laboratory and no software.

Review the sheet monthly, not daily. A single day is noise, since one wet mix or one late truck moves every line. Four weeks shows whether the cement dosage drifted, whether the meter is climbing, and whether the reject pile is pointing at the pallet fleet or at the curing yard. Those are the changes worth acting on, and they set the cost per block for the rest of the year.

FAQ

Frequently Asked Questions

Can a supplier quote a fixed cost per concrete block?
Not honestly. Cement, aggregate, power, pallet and wage prices are local, so the same line costs different amounts in two countries. A supplier can state the input quantities per 1,000 blocks and the installed capacity, and the buyer multiplies those by local prices. Treat any single figure quoted without the quantities behind it as marketing rather than engineering.
Which input moves the cost per block the most?
Cement, in almost every market. It is only about 10 percent of the block by weight, yet it is the one input bought at a price per tonne several times higher than quarried aggregate, and it usually travels furthest to reach the plant. A small change in dosage therefore moves the material cost more than a change of sand source.
How much cement is in a 20 cm hollow block?
About 1.4 to 1.6 kg for a 390 x 190 x 190 mm block weighing 14 to 16 kg, at a cement content near 10 percent of the mix by weight. A block specified for a load bearing wall can carry more, and a partition block less. Confirm the dosage with a cube test on your own materials before it goes into the cost sheet.
Does a larger machine lower the cost per block?
It lowers the fixed cost per block only when the plant actually sells the extra output. A bigger host spreads rent, supervision and the instalment over more pieces, but it also needs a larger pallet fleet, a larger curing yard and more power capacity. A plant running well below its line capacity carries a higher fixed cost per block than a smaller plant that runs full.
How do I calculate the cost of one block for my own plant?
Measure six quantities over four weeks: cement kilos, aggregate kilos, kilowatt hours per 1,000 blocks, pallet loads per 1,000 blocks, crew hours per 1,000 blocks and the reject rate. Multiply each by your local price, divide the month's fixed cost by the blocks sold, and add the two. The total divided by blocks sold is your cost per block.
Why is the electricity figure per block so low compared with the machine rating?
Because installed capacity is the sum of every motor, and the motors do not all draw at once. The hydraulic pump loads during the press stroke, the vibration motors run a few seconds per cycle, and the pallet feeder moves once per cycle. The nameplate total is real for cable and transformer sizing, while the meter records the actual load curve.
What margin per block should a block plant aim for?
There is no universal percentage, and any figure offered without your volume is unreliable. Work backwards instead: the margin must cover the month's fixed cost plus the return you expect on the investment. Divide fixed cost by the margin on one block and you have the break-even volume, which is the number a lender or a partner will ask you to defend.
How often should the cost per block be recalculated?
Monthly, from the plant's own records, and immediately when a supplier changes a price. Cement and power tariffs move faster than most plants update their sheet, so a cost calculated last year usually understates today's figure. Keep four weekly snapshots on one page and the trend becomes visible before it reaches the profit line.