Block Delivery Lead Time and Order Priority: What a Plant Can Promise

A delivery date is set by curing and pallet space, not by the machine. A plant that quotes from the machine rating promises a date it cannot hold in a busy month.

QUICK ANSWER

Block delivery lead time is set by curing, not by the machine. A block stays on its pallet 20 to 24 hours, needs seven days damp and shaded before it can leave, and a QST6-15 forms 8,640 to 11,520 hollow blocks in one eight hour shift. Order priority is then a written rule: deposit date first, then stock already cured, then penalty exposure. Publish both, and confirm the date only after cement, pallets and a truck slot have been checked.

A block plant sells a product it has not made yet, on a date that depends on curing, pallet space and the weather. The date customers argue about is therefore set by the curing clock and the pallet fleet, not by the forming machine. A plant that quotes from the machine rating alone promises something it cannot hold in a busy month, and the argument that follows costs more than the order was worth.

What sets block delivery lead time in a block plant, and who decides order priority?

Curing sets the floor. A block stays on its pallet under cover for 20 to 24 hours, then needs at least seven days damp and shaded before it is fit to leave the yard, and it reaches its specified strength at 28 days. No machine setting shortens that. Whatever else the plant does, the earliest a block formed this morning can be loaded is about a week later.

Above that floor sit three more clocks: forming hours, pallet availability and truck slots. Forming hours come from the machine and the mould. Pallet availability comes from how many orders are already sitting in the curing area. Truck slots come from the loading face and the clamp. Lead time is the sum of the four, plus whatever allowance the plant keeps for the week when everything arrives at once.

How long does an order take from deposit to loaded truck?

Build the promise in four steps and write each one into the order file, so anybody can recompute it later.

  • Forming days: the ordered quantity divided by the shift output of the machine that will run it, rounded up to whole shifts.
  • Curing days: seven from the end of forming, with 28 days noted separately as full strength. A customer who needs the blocks for load bearing work should be told the difference at the quotation stage, not at the gate.
  • Loading day: one day per order in normal conditions, because every clamp trip has to reach a stack that is already cured and tagged.
  • Allowance: two working days for weather, a power cut, a mould change that overran, or a truck that arrives late. This is the part buyers never see and plants forget to quote.

For a standard hollow block in steady production, that arithmetic lands close to ten working days. The plant that says ten and delivers on the ninth keeps the customer. The plant that says four to win the order is explaining itself on day seven.

How many blocks can one shift form, and what does that mean for a 20,000 block order?

A QST6-15 runs a 15 to 23 second cycle, which is 156 to 240 moulds per hour. With six hollow blocks of 390 x 190 x 190 mm per mould, one eight hour shift forms 8,640 to 11,520 blocks. A QST8-15 on a 980 x 860 mm pallet carries more mould area per cycle, and a QST1500 on a 1,350 x 1,150 mm pallet more again, so the same crew covers a higher band without a second machine.

A 20,000 block order is therefore about two shifts of forming. That sounds like two days and is in practice a week and a half, because forming is the fast part of the job. The same order also commits 28 to 32 tonnes of cement at 1.4 to 1.6 kg per 15 kg hollow block, plus pallets for every block that will sit in curing. Both numbers have to be checked before a date is confirmed, and neither of them appears on the machine nameplate.

The pallet count is the one that surprises new plants. A single shift on a QST6-15 with 24 hour curing holds roughly 1,250 to 1,920 pallets in circulation. Two orders in the yard at the same time share that fleet, so accepting the second order can delay the first one even though the machine has spare hours.

Which order gets the machine first when two customers want the same week?

Decide the ranking rule before the conflict, publish it in the quotation, and apply it without exception. A workable order of priority is: written order with deposit received, date of that deposit, product already cured and ready to load, contract with a penalty clause, and finally haulage already booked. Repeat business is a tie breaker inside the same rank, never an override of it.

The rule matters because every alternative is worse. Ranking by who telephoned last rewards pressure rather than commitment, and the customer who paid first learns that a deposit buys nothing. Ranking by order size invites a large buyer to jump a queue that a small buyer has already planned a crew around. A published rule lets the plant refuse a request without insulting anybody: the answer is the same for every customer, and it is written down.

Deposits do real work here. They convert a verbal enquiry into a claim on forming hours, and they give the plant a reason to hold pallets and curing space for that product. A plant that accepts orders without a deposit is not running an order book, it is running a list of intentions. The commercial side of that arrangement belongs with payment terms, which cover how the money is staged.

Why does a special block size cost more lead time than a standard one?

A different block size means a different mould, and a mould change stops the line. The changeover itself consumes part of a shift, and the first pallets off the new mould are checked for dimension, density and surface before the run is released, so a few pallets are scrapped by design. That cost is predictable and should be quoted as part of the lead time for a non standard item.

Less predictable is the mould itself. A mould set is a purchased item with its own delivery window, and it is made to the drawing rather than picked off a shelf. If the mould is not on site when the order is accepted, machine hours are irrelevant, because there is nothing to form the block with. Ask for the mould position before promising a date for any size the plant does not already run.

What does a split delivery do to the promise and to the cost?

Splitting an order into two or three loads keeps a contractor supplied while the plant keeps forming, and it is often the right answer for a project that pours in phases. It also doubles or triples the loading events, and loading is the slowest manual step in the yard. A clamp trip carries 40 hollow blocks, so a 1,000 block release is 25 trips between stack and truck, each one forklift time, driver time and a gate pass.

Split loads also demand identification. Each stack released early has to be tagged with the customer, the order number, the mould date and the quantity, because two orders of the same block in the same yard look identical and cannot be untangled later. A plant that blends two customers into one stack to save space will eventually load one customer's blocks onto the other customer's truck.

What should the plant do when it cannot meet a confirmed date?

Telephone before the truck is dispatched, not after it arrives. The customer can usually absorb a two day slip if they hear about it while they still have time to move a crew; the same two days discovered at the gate become a stopped pour and a permanent loss of trust.

Bring three options to that call: release the part of the order that is already cured, substitute another size that is cured and can do the same job, or give a new firm date with the reason attached. Do not offer a discount as the first move. A discount buys one quiet week and teaches the customer that a late date has a price, which turns every future order into a negotiation about delay.

Which checks belong on the order acceptance sheet?

Five checks decide whether the date can be promised. Run them before the confirmation is sent, and record who signed each one.

CheckWhat it provesWho signsIf it fails
Deposit received and order in writingThe customer has committed, so the hours can be reservedSalesHold the date, do not confirm it
Mould available for the ordered sizeThe block can actually be formed on the promised dayProductionQuote the mould date as the earliest start
Cement and aggregate cover the run28 to 32 tonnes of cement for 20,000 blocks is in the silo or on orderStoreOrder material before the date is offered
Pallets free for the curing daysThe blocks have somewhere to sit for a weekProductionPush the date or hire pallets
Truck slot booked with the haulierLoaded blocks leave the gate instead of occupying the faceDispatchMove the loading day, not the curing day

The sheet is short on purpose. A plant that cannot answer these five questions in a minute is deciding its delivery dates by hope, and hope is the reason customers ask for a discount before they ask for a date.

Which numbers belong on the order confirmation?

Eight fields turn a promise into something both sides can check: product and dimensions, quantity, mould date, curing release date, loading date, truck slot, unit price and payment stage, and the name of the person who confirmed the date. Add the storage rule, because blocks left in the yard beyond the agreed collection window occupy curing space that the next order needs.

Written confirmation also settles the argument about strength. If the blocks are released at seven days, the document should say so, and both sides should understand that the 28 day figure is the design strength rather than a shipping date. Buyers who want the curing background can read the curing guide; the pallet arithmetic behind the queue is set out in the pallet planning guide.

How does the order book connect to the weekly production plan?

The order book is the input, the production plan is the decision. Each week the plant converts confirmed orders into forming hours per product, pallets per curing day and truck slots per loading day. When the three do not fit, something has to give, and it is cheaper to give on a date quoted this week than on a date already confirmed last month.

That is why the sales desk needs the same numbers the planner uses. A salesperson quoting from a price list without the curing calendar will promise the same week to three customers and then explain the shortfall to all three. The weekly plan itself, including shift and mould decisions, is covered in production planning for a block factory, and the loading face that constrains dispatch is described in finished block yard and truck loading.

Plants that run this discipline discover a second benefit. A published lead time of ten working days, held for a year, becomes a selling point that no discount can buy, because contractors plan pours around suppliers they can rely on. The machine is the same machine the competitor has. The order book is what makes the difference.

If you are setting up a plant and want the delivery model built around your machine, your product mix and your site, tell us the block sizes you intend to sell and the monthly volume you expect. We will send the forming, curing and loading arithmetic with the layout so the first date you quote is one you can keep.

FAQ

Frequently Asked Questions

How long is the lead time for a block order?
For a standard hollow block in steady production, about ten working days. Forming takes one or two shifts, curing holds the blocks on pallets for at least seven days, and loading takes a day. Add two working days of allowance for weather, power cuts or a late truck, and quote that figure rather than the machine rating.
Can a block plant deliver an order in seven days?
Seven days is the earliest possible release, not a normal lead time, because the block needs 20 to 24 hours on the pallet plus seven days damp and shaded before it can leave. To hit seven days the plant must form on day one, have pallets free, and have a truck waiting on day eight. Anything less than that is a strength risk.
Who gets priority when two customers order the same product?
The customer whose deposit arrived first, unless the second order is already cured in the yard or carries a penalty clause that the plant has accepted in writing. The rule should be printed in the quotation. Ranking by telephone pressure or by order size destroys the value of a deposit and makes every future date negotiable.
Should a block plant take deposits on orders?
Yes, and for an operational reason as much as a financial one. A deposit converts an enquiry into a claim on forming hours, pallets and curing space, and it gives the plant a defensible answer when a second customer wants the same week. Orders held without a deposit are intentions, and intentions do not survive a busy month.
What happens if the curing is not finished on the promised date?
The plant should telephone before the truck is dispatched and offer the cured part of the order, a cured substitute size, or a new firm date with the reason attached. Loading green blocks to protect a date is the one option that must be refused, because the failure appears on the customer's wall a month later, not at the gate.
How many blocks can be loaded in a day?
Loading is limited by clamp trips rather than by weight. A clamp carries 40 hollow blocks per trip, so 1,000 blocks is 25 trips between stack and truck, each one forklift time, driver time and paperwork at the gate. With one loading face, that is a working day's dispatch for most small and mid size plants.
Does a special block size change the delivery lead time?
It does, for two reasons. The mould change stops the line for part of a shift and the first pallets off the new mould are checked and partly scrapped. More important, the mould set is a purchased item with its own delivery window, so if it is not on site when the order is accepted, machine hours cannot help.
What should the order confirmation include?
Product and dimensions, quantity, mould date, curing release date, loading date, truck slot, unit price with payment stages, the storage rule for blocks left in the yard, and the name of the person who confirmed the date. Those eight fields let both sides check the same promise instead of arguing about what was said on the telephone.