Production Planning for a Block Factory: Shifts, Moulds and Curing
The weekly plan that links machine cycles to delivery dates: one or two shifts, mould sequence, curing pipeline, cement tonnage and the maintenance window.
Production planning for a block factory comes down to five weekly decisions: how many shift hours to run, which products in which order, how many pallets to hold in curing, when mould changes happen, and when maintenance runs. A single QST6-15 shift covers 8,640 to 11,520 hollow blocks, so a second shift doubles output but also doubles pallets, curing places and crew. Curing time, not machine capacity, sets what the plant can actually deliver.
A block plant with enough capacity and no plan looks busy and delivers late. The machine runs, the yard fills, and then on Thursday there are four thousand blocks of a type nobody ordered sitting under a tarpaulin, while the three thousand blocks the customer wanted tomorrow are still two days short of curing. Nothing is broken. The plant simply produced what was easy to produce instead of what was sold.
Production planning for a block factory is the link between the machine's cycle and the delivery note, and it is the part of the project nobody buys. A line is ordered, installed and commissioned around output figures, and then the first working month is spent discovering that the curing yard, not the machine, decides how much the plant can sell. Planning is how that discovery is made on paper instead of in front of a customer.
What does production planning for a block factory have to decide each week?
Five decisions, and everything else follows from them. How many shift hours to run this week. Which products in which order, because a mould change costs half a shift and a colour change costs a cleaned mixer. How many pallets to hold in the curing yard and for how many days, because that number caps everything upstream of it. When the mould changes happen, and when maintenance happens, because both want the same free window. And how much cement and aggregate to have on the ground before the week starts.
Written down, those five decisions fit on one page. Left unwritten, they are made every morning by whoever is standing closest to the machine, and the plant's real output becomes an accident of who was on shift.
One shift or two, and what does the second shift actually cost?
The machine output is the easy half of the comparison. A QST6-15 forming six hollow blocks per cycle covers 8,640 to 11,520 blocks in an eight hour shift, so a second shift doubles that to a band of 15,024 to 23,040 blocks a day depending on the cycle the plant actually holds. What matters is everything that has to double with it, because the machine is the only part of the plant that does not need a copy.
| Item | One shift | Two shifts | Constraint it creates |
|---|---|---|---|
| Daily output, QST6-15, 20 s cycle | 8,640 blocks | 17,280 blocks | Sales volume and delivery trucks |
| Pallets in circulation | 1,440 per shift cycle | 2,880 per day | Pallet stock and the cash tied up in it |
| Curing yard places | One day of production | Two days of production | Land under cover, forklift travel distance |
| Crew on the line | Six to eight | Twelve to sixteen | Supervision on the second shift, not just bodies |
| Maintenance window | Between shifts, daily | One short gap, weekly | Unplanned stops become the maintenance plan |
| Cement and aggregate | One day of consumption | Two days | Silo size, delivery reliability |
| Energy per block | Baseline | Slightly lower | Fixed demand spread over more product |
The second shift is worth running when the curing yard can take the volume, the pallet stock can cover the extra day, and the order book can absorb it without cutting price. It is not worth running when the plant would be producing blocks it has to stack in the open, because the second shift then converts electricity and labour into inventory that loses value as it weathers.
How does curing time set the whole schedule?
A block cannot be sold on the day it is made. Whatever the line produces today enters the curing yard and stays there for days, so the delivery leaving the gate today was produced earlier in the week. That single fact turns production planning into pipeline management: the plant is always producing for a delivery date that is several days ahead, and a rush order cannot be met today, only brought forward within the pipeline.
In practice a covered yard holding hollow blocks for a few days before dispatch is enough in most climates, longer in cold weather, and the number of days is the multiplier that sets the pallet count. If the plant plans four curing days, it needs four days of production in pallets in the yard at all times, which for a single shift at 8,640 blocks is 5,760 pallets plus what is in the machine and on the truck. The pallet calculation and the curing routine belong in the same week of planning, because they are the same decision seen from two sides.
Which product should run first in the week?
Order by how long the product needs to become sellable, not by how easy it is to make. Thick hollow blocks and solid units go first in the week so that they are curing while the paver and face mix run later. Coloured products and thin pavers run last for a second reason: a colour change needs a mixer that is genuinely clean, and grey residue in a coloured face mix shows up as a streak on every block from that batch.
| Day | Shifts | Product | Mould | Curing bay | Why it sits here |
|---|---|---|---|---|---|
| Monday | Day and night | Hollow block, main type | Six cavity | 1 to 4 | Largest order first, longest curing time |
| Tuesday | Day and night | Hollow block, main type | No change | 5 to 8 | Feeds the same delivery as Monday |
| Wednesday | Day | Hollow block, second type | One change | 1 to 4 | Half a shift lost to the change |
| Thursday | Day and night | Grey pavers | One change | 5 to 8 | Mixer cleaned before any colour runs |
| Friday | Day | Coloured pavers | No change | 9 | Last colour of the week, least residue risk |
| Saturday | No production | None | Inspection | None | Oil, pallets and wear parts in the free window |
Group the week into as few mould changes as the order book allows. A mould change on an automatic line is not a five minute job: it is a block of hours with a small crew, a lifting point, a first pallet that has to be checked and often a setting adjustment on the feed. Two changes a week is comfortable, five is a plant that spends its week fitting rather than forming.
How much cement and aggregate does a week consume?
Start from block weight and work backwards. A 390 x 190 x 190 mm hollow block weighs roughly 14 to 16 kg, so a shift of 8,640 blocks is about 130 tonnes of product leaving the machine. With cement at roughly 10 percent of the mix by weight, that shift consumes around 13 tonnes of cement and something near 115 tonnes of aggregate and sand, and a five day week at one shift is therefore about 65 tonnes of cement.
That number is what makes the silo decision, and it is usually the argument for a 100 tonne silo rather than a 50 tonne one: it holds a week of single shift production, so a late cement delivery costs you a day rather than a week. A two shift plan doubles both figures and makes the silo and the aggregate stockpile a weekly rather than a monthly concern.
Where does the maintenance window go?
Between shifts, on the same day every week, and protected like a delivery. The plant that plans maintenance at the end of the month ends up doing it during an unplanned stop, on the shift when a customer is waiting. Put the mould change, the oil check, the pallet inspection and the wear part inspection in one window and give it an owner, as set out in the maintenance schedule.
Do not plan a mould change and a maintenance window on the same day. Both consume the same free hours, and a plant that tries to do both starts the week with a machine that is neither serviced nor set up.
What changes on a night shift?
Supervision, light and moisture. A night shift with no supervisor on the floor is a shift where the cycle slowly stretches and the reject pile grows without anyone writing it down. Lighting over the pallet magazine and the stacking area is a maintenance item, not a comfort item, because an operator who cannot see the pallet edge will mis-stack it. And curing does not wait for morning: if nobody sprays at two, the blocks produced at midnight start their first day dry.
Plan the first month of a night shift at 85 to 90 percent of the day shift output and let it earn the rest. The crew that is trained on days needs a different rhythm at night, and the training plan should include one supervised night before the shift is handed over.
When should a plant add a machine instead of another shift?
When the second shift has been running at its output ceiling for a full season, when the curing yard is the thing that cannot grow further without more land, and when the order book is limited by moulds rather than by hours. Until all three are true, a second machine adds capital, foundation, power capacity and a second crew, and it does not solve a pallet or a yard problem. The expansion decision is a capacity question, and capacity bought before the pipeline can carry it is capacity that sits still.
Which five numbers belong on the weekly planning sheet?
Blocks per shift against plan, reject percentage with the top cause named, cement kilograms per block, downtime minutes by cause, and on time delivery percentage for the week. Those five tell you whether the plan was wrong or the plant was, which is the only distinction worth making on a Monday morning.
Add one more while the plant is young: pallets in the yard at the start and end of the week. It is the number that predicts next week's output better than any other, and it is free to count.
Tell us the block types you sell, the moulds you own and the delivery lead time your customers expect, and we will put the shift structure, the mould sequence and the curing pipeline into the plant plan with your own figures.
Frequently Asked Questions
How do you decide between one shift and two shifts in a block factory?
How many days should blocks cure before delivery?
How long does a mould change take on an automatic line?
How much cement does a block plant use in a week?
Can a block plant take a rush order for delivery this week?
What should the weekly production sheet record?
How does a night shift change output and quality?
When should a plant buy a second machine instead of running a second shift?
Related machines

Concrete Block Making Machine
Core machine for hollow blocks, solid blocks, pavers and curbstones.

Automatic Block Making Machine
High-output automatic block machine for industrial production lines.

Hydraulic Block Making Machine
Hydraulic forming system for stable density and consistent blocks.

Hollow Block Making Machine
Machine configurations for common hollow concrete block sizes.