Capacity planning

Expanding a Block Plant: Where the Extra Capacity Comes From

A running block plant is usually limited by pallets, curing space or batching rather than by the press. This page sets out how to measure the bottleneck, what a second shift adds, and the order in which capacity should be bought.

QUICK ANSWER

Expansion starts with measurement, not with a new machine. A QST6-15 runs 156 to 240 moulds per hour at its 15 to 23 second cycle, so a plant delivering far less is limited by pallets, curing lanes, batching or changeover. Clear those first, then add a second shift, which doubles daily output on the same host, then the pallet fleet, and only then a second machine of the same pallet size.

A block plant that already runs does not usually need a bigger machine. It needs the bottleneck removed. Most owners who feel they are short of capacity are running a host with a published rating of 8,640 to 11,520 hollow blocks per 8 hour shift, and the way that rating relates to real output is set out in the block machine capacity guide and shipping 5,500 to 6,500, and the difference is almost never the press. It is pallets waiting, curing space, a mixer that cannot keep up, or changeover time that nobody counted.

This page is about the decision that follows: whether expanding a block plant is the right move at all, and in what order the work should go, so that the money goes into the part that is actually holding output back. The same method applies whether the plant makes hollow blocks, pavers or solid bricks, because the limit sits on the complete concrete block production line rather than on any single unit of it.

Which bottleneck actually limits a block plant?

Start with a measured number rather than a feeling. Log the forming cycle for three full shifts and write down every stop longer than one minute with its cause. A QST6-15 has a forming cycle of 15 to 23 seconds, which is 156 to 240 moulds per hour. If the line is running 189 moulds per hour, the machine is at its mid range and is not the problem. If it is running 120, something outside the machine is stealing one third of the day.

In our experience of commissioning lines in the Middle East, the causes sort into four groups, in this order of frequency: the pallet fleet is too small for the curing time, the curing area has no free lane, the mixer or the batching plant waits on cement or aggregate, and product changeover takes longer than planned because moulds are changed cold and settings are re-tuned by trial.

Only when all four are cleared does a second machine make sense. Buying a host to cover a pallet shortage is the most expensive way to solve a pallet shortage.

How much output does a second shift add?

A second shift doubles the output of the same machine with no foundation, no new transformer and no new moulds. On a QST6-15 that means 17,280 to 23,040 hollow blocks per day instead of 8,640 to 11,520, at the same capital cost as the plant you already own.

The precondition is that the plant can absorb 24 hours of production, not 8. Curing space has to hold two shifts of filled pallets instead of one, so the pallet fleet roughly doubles and the curing lanes double with it. Cement and aggregate stock has to cover a full day of consumption, which usually means a second silo or a larger one. Staffing has to be split into two crews, and an automated line of the QSRGV type is quoted at 3 to 4 workers per line per shift, as described in the staffing and operator training plan, so two shifts means 6 to 8 trained operators plus a mechanic on call.

The cost of a second shift that is often forgotten is the maintenance window. If the machine runs 16 hours and stops 8, all cleaning, mould checks, hydraulic inspection and pallet straightening happen in those 8 hours. Plants that skip the window for a month pay for it in a week of breakdowns.

When is a second host better than pushing the first one?

Four routes exist, and they are not interchangeable. The table compares what each one actually adds and what it demands from the site.

RouteOutput addedWhat must exist firstWhere it stops working
Second shift on the same hostPlus 100 percent, 8,640 to 11,520 becomes 17,280 to 23,040 hollow blocks per day on QST6-15Double pallet fleet, double curing lanes, second crew, day stock of cement and aggregateWhen curing area cannot hold a full day of filled pallets
Stabilise the cycle at the fast endFrom 23 to 15 seconds is 156 to 240 moulds per hour, about 50 percent more from the same machineMix design checked, vibration and pressure set by test, mould in good condition, pallet flatness verifiedWhen the mix or the aggregate will not support the shorter cycle
Add a second host of the same pallet sizeA second 8,640 to 11,520 per shift on the same pallet and mould familyFoundation, power headroom, second pallet fleet, second stacker, more curing lanesWhen the mixer and batching plant cannot feed both hosts
Replace the host with a larger modelQST8-15 on a 980 x 860 mm pallet compared with QST6-15 on 980 x 680 mmNew pallet fleet, new moulds, new foundation, revised powerCapital, and the old pallets and moulds become scrap value

Note the trap in the fourth row. A larger host is not an upgrade of the same line, it is a new line, because the pallet changes and every mould in the store stops fitting. If the pallet fleet is healthy and the curing area has room, a second host of the same pallet size keeps the whole spares and mould inventory working.

What does the site have to carry before a second machine goes in?

Power first. One QST6-15 line draws 34.4 kW at the host, 29.5 kW at the QS-1200A palletizer, 3 kW at the pallet feeder and 25.5 kW at a JS500 mixer, which is about 92 kW of connected load before conveyors, compressors and lighting. Two such lines need a transformer and a main cable sized for the total, not for the sum of nameplates added later. The electricity guide explains how those figures relate to the monthly bill.

Foundation second. QST6-15 measures 9,450 x 3,300 mm and weighs 12 t, QST1200 measures 11,500 x 4,550 mm at 17 t, and QST1500 measures 11,500 x 4,500 mm at 20 t. The second host needs its own reinforced slab with anchor bolts set from the general arrangement drawing, cured before the machine lands. Pouring a slab next to a running line is possible, but the excavation must not undercut the existing foundation.

Third comes the pallet fleet. With a 24 hour curing time, the number of pallets in circulation sets a hard ceiling on daily output: at 6 hollow blocks per mould, 1,000 pallets support 6,000 blocks per day and no more, whatever the machine is rated. A second host with the same pallet count simply makes each pallet turn faster and buys nothing. The pallet count is covered in detail on the page on pallets for a block production line.

Can the existing mixer feed a second host?

The QS-1200 twin shaft series is quoted at 25, 35, 50 and 75 cubic metres per hour for the JS500, JS750, JS1000 and JS1500, at 25.5, 39.35, 50.2 and 75 kW. Compare that with the concrete the host actually consumes.

Take a solid standard brick of 240 x 115 x 51 mm, which is 0.0014 cubic metres of concrete per piece. At 34 bricks per mould and a 20 second cycle, the host makes 6,120 bricks per hour, which is 8.6 cubic metres of concrete per hour. Adding a planning allowance for waste, the demand is close to 9 cubic metres per hour. One QST6-15 therefore sits comfortably inside a JS500 at 25 cubic metres per hour, and two hosts at 18 cubic metres per hour still fit, but with little margin for a slow batching cycle or a wet mix.

For hollow blocks the check runs the other way. A 390 x 190 x 190 mm block has a gross envelope of 0.014 cubic metres, so 6 per mould at 200 moulds per hour is 16.9 cubic metres per hour of envelope. Actual concrete is lower because of the voids, but the figure is a useful ceiling: if the mixer cannot deliver that envelope, it cannot deliver the line.

What breaks first when a line is pushed above its plan?

Pallets bend before machines do. A pallet that has been through thousands of cycles picks up a bow of a few millimetres, and a bowed pallet produces blocks of uneven height, which then jam the stacker. Pallet face buildup from cured concrete does the same thing more slowly and is easier to miss.

The stacker is the second limit. The QS-1200A palletizer has a single layer cycle of about 18 seconds against a host cycle of 15 to 23 seconds, so at the fast end of the host range the stacker has almost no slack, and every stoppage has to be recovered inside the shift. The pallet feeder holds 3 stacks and cycles in about 13 seconds, which sets how long the line can run between refills.

The third limit is the forklift clamp. The QS-1200 clamp lifts 2,000 kg and carries 500 to 800 standard bricks or 40 hollow blocks per lift, working with stacks of 1,000 x 1,000 x 1,000 mm. If the expansion doubles output, the yard handling doubles too, and one clamp will not cover two hosts across a full shift.

How should expanding a block plant be sequenced?

Measure for one week, clear the four bottlenecks in the order they cost output, then add the second shift, then the pallet fleet and curing lanes, and only then the second host. Upstream equipment such as the batching plant and the cement silo comes last, because they are the easiest to oversize and the least useful to oversize early.

A plant that treats expanding a block plant as a sequence rather than a purchase usually finds that the second host can wait a year, and that the money spent on pallets and curing lanes paid for itself in the first quarter. A plant that buys the host first spends the same money and still ships the same number of blocks, because the pallets and the curing floor are still the limit.

What should the buyer ask the supplier for?

Ask for the general arrangement drawing of both lines on the same site plan, the anchor bolt layout, the connected load schedule per unit, and the pallet count the supplier assumes in the output figure. If the supplier quotes output without stating a pallet count and a curing time, the number is a machine rating, not a plant capacity.

Commissioning is the last item. A second line added to a running plant is commissioned around production, the sequence covered in the guide on installing a block line in the Middle East, which means the acceptance test is usually run at night or on a low demand product. That is normal, and it should be written into the schedule before the containers are booked.

FAQ

Frequently Asked Questions

How do I know whether my block plant needs a second machine?
Measure the forming cycle over three full shifts and log every stop longer than one minute with its cause. If the host is running 156 to 240 moulds per hour, which is the 15 to 23 second range of a QST6-15, the machine is not the limit and a second machine will not raise output. Fix pallet supply, curing lanes, batching and changeover first, then re-measure before spending on a host.
How much more can a second shift produce on the same block machine?
A second shift doubles the daily output of the same host, so a QST6-15 rated at 8,640 to 11,520 hollow blocks per 8 hours reaches 17,280 to 23,040 per day with no new machine and no new foundation. The plant must be able to absorb a full day of production, which means roughly double the pallet fleet, double the curing lanes, a day of cement and aggregate stock and a second trained crew.
Is it cheaper to add a second block machine or to replace the old one?
A second machine of the same pallet size keeps every mould and every pallet in the store working, so the only new cost is the host, its foundation and the shared handling equipment. Replacing a QST6-15 with a QST8-15 changes the pallet from 980 x 680 mm to 980 x 860 mm, which invalidates the whole pallet fleet and the whole mould set. Replacement only pays when the old machine is at the end of its life.
What power supply does an expansion need?
One QST6-15 line connects 34.4 kW at the host, 29.5 kW at the QS-1200A palletizer, 3 kW at the pallet feeder and 25.5 kW at a JS500 mixer, about 92 kW before conveyors, compressors and lighting. A second line of the same size needs a transformer, main cable and protection sized for the combined load. Size the transformer for the planned plant, not for the plant that exists today.
Can the mixer keep up if I add a second host?
Check the concrete demand first. A solid 240 x 115 x 51 mm brick needs about 0.0014 cubic metres of concrete, so 34 bricks per mould at a 20 second cycle is roughly 8.6 cubic metres per hour, about 9 with a waste allowance. A JS500 is quoted at 25 cubic metres per hour, so it covers one host comfortably and two with limited margin. A JS750 at 35 cubic metres per hour leaves real headroom.
How long does it take to bring a second line into production?
The sequence is foundation, curing of the slab, machine erection, mechanical and electrical connection, dry running, then commissioning around the existing production. Most of the calendar time is in the foundation curing and in the shipping of the second set, not in the assembly itself. Commissioning is normally scheduled at night or on a low demand product so the first line keeps shipping.

Related machines

NEXT STEP

Get a project-specific price, not a catalog number.

Request Quote →
WhatsApp