Block Plant Warranty and After-Sales: What the Contract Must Fix

A warranty is only useful when five lines are written before the deposit: period, parts against labour, excluded wear items, claim evidence and the response window. This page shows what each line should say.

QUICK ANSWER

A block plant warranty and after-sales clause should fix five things in writing before the order: the period and its start date, the split between parts and labour, the wear items excluded such as moulds and pallets, the evidence a claim needs, and the response window. Most disputes come from a clause that named a period without a parts list, or that left freight and site labour to be discussed during a stoppage.

What should a block plant warranty and after-sales clause settle before the order?

A block plant warranty and after-sales clause should fix five things in writing: the period, the split between parts and labour, the list of wear items excluded, the evidence a claim needs, and the window for a first response. When any of the five is left verbal, the buyer discovers the gap on the morning the machine stops, which is the worst possible moment to negotiate.

Terms differ from project to project, because a single machine, a full line and a line with a curing system carry different risks. That is why the useful work happens before the deposit: the clause is compared across quotations the same way the equipment list is, and the difference between two offers often sits in these five lines rather than in the price.

Which parts belong inside the warranty and which are wear items?

The dividing line is consumption, not price. A part that is expected to be consumed by production, or replaced on a known interval, belongs outside the warranty and inside the spare parts budget. A part that fails because of a manufacturing defect inside its design life belongs inside. Most disputes come from a quotation that never separated the two.

ItemUsual treatmentWhy it falls there
Hydraulic pump, motor windings, gearboxInside the warranty periodFailure is a defect, not consumption, if the oil and pressure were kept to the schedule
PLC, controller, inverter, proximity switchesInside the warranty periodElectronic failure is not caused by block production
Vibration exciter bearingsDepends on the clause, read itThey run at 3,800 to 4,500 cycles per minute and wear with hours, so some contracts cap them by running hours
Moulds and mould linersOutside, wear itemConsumed by the block itself, and life depends on the mix abrasive content
PalletsOutside, wear itemStruck by the press every cycle and washed in curing
Mixer blades and liners, seals, filters, oil, hoses, beltsOutside, wear itemReplaced on interval or on condition by definition
Structural welds and frame cracksInside, and worth namingThe most expensive failure to argue about later, so it should not depend on interpretation

Ask for the table above to be filled in for your own quotation with the same item names. A clause that says the machine is warranted for a period, without a parts list, is not a warranty that a plant manager can use.

Why does the site voltage decide whether a claim is paid?

Every electrical failure claim begins with the supply, because the wrong voltage destroys a motor winding or a drive in minutes and no manufacturer covers that. A line built for 380 V three phase, connected to 415 V or to a 60 Hz supply without the right configuration, ends in a claim that is refused on the first page of the report.

This is settled before the order, not after arrival. The plant should state the supply voltage, the frequency, the number of phases and whether a transformer or a generator is part of the design, and the quotation should repeat those figures back. A generator that drops frequency under load is the second most common cause of a refused claim, and it is invisible in the quotation unless the clause mentions it. The supply figures themselves belong in the power supply plan, which is settled before the order and not after arrival.

What maintenance evidence does a claim need?

A claim stands or falls on the record that already existed before the failure. That record is short and cheap to keep: the pressure reading at the start of every shift against the rated figure of the model, which is 25 MPa on a QST6-15, 31.5 MPa on a QST8-15 and across the QS static press range, and 21 MPa on the QSMT1000 pallet free machine.

The rest of the record comes from the maintenance schedule and spare parts stock. Add the oil level and oil temperature, the monthly oil sample, the weekly straightedge and caliper check on the mould face, and the sampling of five pallets per shift for flatness and corner cracks. None of these tasks takes more than a few minutes, and together they answer the only question the factory will ask: was the machine run inside its limits. A warranty clause that does not require the log is generous on paper and hard to enforce in practice, because the failure cannot be attributed either way.

How is a claim handled when the plant is far from the factory?

Distance changes the sequence, not the principle. The first hour is for evidence, not for opinions: stop the machine, photograph the failed part in place, record the model and serial number, the pressure reading, the product and the batch, and film the symptom with sound where the fault is audible. A bearing on its way out changes the sound before it changes the block, and a ten second recording often replaces a week of messages.

The second step is a decision on the part. Small critical parts travel by air, heavy parts by sea, and the clause should say which category each falls into and who pays the freight. The failed part should be kept rather than discarded, because an inspection on arrival is how a defect claim is closed, and a part that was thrown away closes the claim in the wrong direction.

Labour on site is the third question, and the one most often left out. If the buyer's own technician replaces the part, the clause should say whether that labour is covered, and if a factory engineer travels, whether the ticket and the accommodation are part of the warranty or a separate service. Writing this down protects both sides from a discussion held during a stoppage.

What does after-sales cover beyond spare parts?

Training that survives staff turnover is the most valuable part of after-sales and the least often written into the offer. A crew trained once at commissioning loses the skill when two operators leave, and the plant then runs at a lower cycle without anyone calling it a fault. A refresher at the change of season, or after a mould change to a new product, costs a fraction of a service visit and protects the output figure.

Remote support belongs in the same list. With a messaging channel and the controller screen, most setup questions are answered in an hour: a cycle that will not hold, a stacker that misaligns a layer, a mix that tears at the mould edge. The clause should name the channel and the person, because a channel that nobody answers is worse than no channel at all.

Which documents should be handed over with the line?

The handover pack is the part of after-sales that keeps working after the warranty ends. It should contain the foundation and anchor bolt drawings, the layout as built, the electrical schematic, the hydraulic schematic, a backup of the PLC program, the operation manual in the language the crew reads, and the spare parts list with part numbers that can be ordered years later.

Two documents are usually missing and both matter: the acceptance record from commissioning, with the cycle and the output actually measured on the agreed product, and the mould drawings for every product the plant intends to make. Without the acceptance record, a later output dispute has no baseline. Without the mould drawings, a replacement mould becomes a new project instead of a purchase order.

What should be written about response time?

Response time is worth agreeing, and it is worth agreeing in parts rather than as one promise. A first response window, a parts dispatch window for stock items, and a named channel for each are three lines that a plant manager can actually use. What matters is that the three are measured in the same unit, usually working days, and that holidays on both sides are named.

The same clause should say who pays for what: freight on a warranted part, labour on site, and the travel of an engineer when one is needed. A warranty that covers the part but not the freight to a plant in the Middle East is a discount, not a warranty, and it is better to see that on the quotation than on the invoice.

Send the equipment list and the supply voltage, and the warranty and after-sales scope can be written against the actual configuration of your line rather than a generic promise.

FAQ

Frequently Asked Questions

How long should a block plant warranty last?
The period is set per project in the contract, and it usually follows the equipment type rather than the whole line: the host and the electrical package carry one period, the curing line and the cuber another. What matters is that the period is written with a start date, normally handover after the acceptance run, not the shipping date.
Are moulds and pallets covered by a block plant warranty?
They are normally treated as wear items and excluded, because both are consumed by production. Mould life depends on the abrasive content of the mix and pallet life depends on how the press and the cuber handle them, so a defect claim on either is hard to separate from use. Budget for both in the spare parts plan.
What voids a block plant warranty?
The usual grounds are a wrong supply voltage or frequency, non-original critical parts, skipped oil and filter intervals, and running the machine outside its rated pressure. Each of these is recorded in a document the plant already keeps, which is why the shift log matters more than the wording of the clause when a claim is filed.
What evidence should a buyer keep for a warranty claim?
Photographs of the failed part in place, the model and serial number, the pressure reading at the start of the shift, the product being made and the batch, and a short video where the fault can be heard. The failed part itself should be kept for inspection instead of being discarded during the repair.
Does after-sales include operator training after commissioning?
It should include a refresher, and the contract is the place to fix how many days and when. A crew trained once loses the skill when operators leave, and the plant then runs below its cycle without anyone recording a fault, so a short refresher is cheaper than the output it protects.
Who pays freight on a warranted spare part?
That is a contract line, and it differs between suppliers. On a warranted part the freight is often shared or covered by the supplier, while on a wear item the buyer pays. Ask for the rule in writing before the order, because air freight for one critical part can exceed the price of the part itself.
Which documents must be handed over with a block production line?
Foundation and anchor bolt drawings, the as-built layout, electrical and hydraulic schematics, a PLC program backup, the operation manual in the crew language, the spare parts list with part numbers, the mould drawings, and the acceptance record showing the cycle and output measured at commissioning.