Power Supply for a Block Plant: Connected Load and Generator Sizing
Connected load, current and kVA for each host and mixer, transformer and generator sizing, why the site voltage is fixed at order stage, and the protection a block plant needs.
A block plant is sized on two numbers: connected load and the largest motor start. A QST8-15 with a JS750 mixer, pallet feeder and QS-1200A palletizer reaches about 120 kW, roughly 214 A at 380 V and 141 kVA, so the transformer step is 160 or 200 kVA. The generator needs about 25 percent headroom above running load and must accept the mixer starting at six to seven times full load current.
A block plant is designed twice. First as a layout, which everyone discusses, and then as an electrical single line diagram, which usually gets settled late, by whoever is wiring the site. The second drawing decides whether the line starts on the day the installation team arrives, or waits three weeks for a transformer that was ordered after the foundation was poured.
Two numbers carry the whole decision: the connected load of everything that runs at the same time, and the starting current of the largest motor. The first sizes the transformer and the cable, the second sizes the generator.
How much power does a block plant need?
The connected load is the sum of the host machine, the mixer, the pallet handling equipment and the conveyors, plus lighting, a compressor and a water pump. Most buyers know the figure for the host and forget that the mixer can draw as much as the press.
Installed capacity is published per model, and it is the number to add up rather than a family average:
| Host model | Installed capacity | Note |
|---|---|---|
| QT4-15 | 22.9 kW | Compact automatic host, 25 MPa forming pressure |
| QST6-15 | 34.4 kW | Plus 3.0 kW for the stacking machine |
| QT5-15 | 37.4 kW | 25 MPa, 1,100 x 650 x 20 mm pallet |
| QSMT1000 | 39.5 kW or 57.5 kW | Two sizes in the pallet-free series |
| QST8-15 | 44.9 kW | Plus 3.0 kW for the stacking machine, 31.5 MPa |
| QS600 static press | 46.9 kW | 31.5 MPa, 850 x 700 mm forming area |
| QS800 unidirectional | 54.9 kW | 31.5 MPa, 1,100 x 680 mm forming area |
| QS1000 unidirectional | 66.4 kW | 31.5 MPa, 1,100 x 850 mm forming area |
| QS800 bidirectional | 70 kW | 31.5 MPa, 18 to 22 s cycle |
| QS1500 unidirectional | 88.4 kW | 31.5 MPa, 1,440 x 850 mm forming area |
| QS1000 bidirectional | 105.4 kW | 31.5 MPa, 600 mm main cylinder bore |
| QS1500 bidirectional | 108.2 kW | 31.5 MPa, 43 t machine weight |
| QST1200, QST1500, QST1800 | From the drawing | Published specifications give size and pallet, not installed capacity |
Then the equipment around the host, which is where a load calculation usually goes wrong:
| Item | Installed capacity | When it runs |
|---|---|---|
| QS-1200 automatic pallet feeder | 3 kW | Continuously, 13 s per feeding cycle |
| QS-1200A low position palletizer | 29.5 kW | Continuously during packing, 18 s per layer |
| JS500 twin shaft mixer | 25.5 kW | Batch cycles, 25 m3 per hour |
| JS750 twin shaft mixer | 39.35 kW | Batch cycles, 35 m3 per hour |
| JS1000 twin shaft mixer | 50.2 kW | Batch cycles, 50 m3 per hour |
| JS1500 twin shaft mixer | 75 kW | Batch cycles, 75 m3 per hour |
| Conveyors, compressor, lighting, pump | Add from the site drawing | Mixed, and never zero |
Two worked examples show how far apart a small and a large line sit. A QST8-15 with a JS750 mixer, a pallet feeder and a QS-1200A palletizer adds up to 44.9 + 3.0 + 39.35 + 3.0 + 29.5 = 119.75 kW, so about 120 kW before lighting and a compressor. A QST6-15 with a JS500 mixer and a pallet feeder, without a palletizer, is 34.4 + 3.0 + 25.5 + 3.0 = 65.9 kW. A QS1000 bidirectional press with a JS1000 mixer, feeder and palletizer reaches 105.4 + 50.2 + 3.0 + 29.5 = 188.1 kW.
How do you turn kilowatts into amps, kVA and a transformer size?
Current on a three phase supply follows the load, the voltage and the power factor:
Amps = watts divided by 1.732 x 380 x power factor. With a power factor of 0.85, the 120 kW line draws about 214 A, the 66 kW line about 118 A, and the 188 kW line about 336 A.
Apparent power is kilowatts divided by the same power factor, so 120 kW needs roughly 141 kVA of transformer capacity. Choose the next standard size above that figure and leave room for the load you will add later, which in practice means a 160 kVA or 200 kVA unit for a single 120 kW line. The utility connection application is the slowest item in the whole project, so the figure is needed months before the machine ships.
| Line example | Connected load | Current at 380 V, 0.85 PF | Apparent power | Transformer step to plan |
|---|---|---|---|---|
| QST6-15, JS500, feeder | 65.9 kW | 118 A | 78 kVA | 100 kVA |
| QST8-15, JS750, feeder, QS-1200A | 119.75 kW | 214 A | 141 kVA | 160 kVA or 200 kVA |
| QS1000 bidirectional, JS1000, feeder, QS-1200A | 188.1 kW | 336 A | 221 kVA | 250 kVA |
Those figures are starting points, not a utility submission. A real calculation uses the actual site voltage, the power factor of the motors supplied, the cable route length and the derating for a hot cabinet. What the table does is fix the order of magnitude early enough that the transformer is not the reason a finished line sits idle.
How big should the generator be?
Bigger than the running load, and sized on the worst starting event rather than on the total. The mixer is usually the largest single motor on a block line, at 39.35 kW on a JS750, and a direct on line start pulls six to seven times its full load current for a few seconds. A generator that matches the running load exactly will drop on that start, and the press control will reset in the middle of a cycle.
The working rule is a continuous rating above the running load with 25 percent headroom, so 120 kW lands at 150 kVA minimum and about 200 kVA with the margin, and the alternator datasheet is then checked for the transient the mixer demands. Below roughly 40 percent of its rating a diesel generator runs cold and wet stacks, so oversizing by two steps costs fuel and engine life as well as money.
Changeover between the utility and the generator needs a mechanically interlocked switch, never a manual plug, and the generator needs its own earth. On a site where the utility drops several times a day, the generator also has to carry the hydraulic power unit while the press is holding pressure, which is the moment a soft supply shows up as a drifting cycle.
Why does the site voltage have to be settled before the order?
Because motors, contactors, the control transformer and any drive on the machine are built for one voltage and one frequency. Machines for this region are configured for 380 V, 50 Hz, three phase supply, and that is stated on the product pages for the block, hollow block and hydraulic press ranges. A site supplied at 415 V or at 60 Hz is a different machine build, not a switch setting.
So the order stage collects four answers: voltage, frequency, number of phases, and whether the plant will run on the utility, a generator, or both. Getting one of them wrong after the machine has shipped means rewinding motors or replacing contactors on site, with the line stopped while it happens.
What protects the line when the supply is unstable?
A phase failure and phase sequence relay first, because a lost phase stops one motor and burns another, and voltage sags are common on the networks that feed industrial zones in the region. Then an under and over voltage relay, a surge arrestor at the incoming panel, and a voltage stabiliser where the utility swings widely through the day.
Inside the plant, the control cabinet needs filtered fan cooling rather than an open door, because a block plant makes dust all day and a dusty drive fails in the hottest week of the year. Cable sizing follows the starting current and the route length, not the running current, and the earth electrode is separate from the neutral bond at the transformer.
How do you estimate the electricity bill?
Multiply connected load by a load factor and by the hours the plant runs, then by the local tariff:
kWh per month = connected kW x load factor x hours per month. The load factor is well below one, because the mixer batches, the press ramps between filling, pressing and ejecting, and the palletizer works in cycles. Until a meter has recorded a month, a range of 0.5 to 0.7 of connected load is a reasonable planning figure for a line in production.
Two habits bring the figure down without touching the machine. Power factor correction at the incoming panel reduces the reactive charge that many utilities bill separately, and shifting the heaviest production into the hours when the tariff is lower, where such a tariff exists, moves consumption without reducing output.
What belongs on the electrical drawing before construction?
A single line diagram with the transformer rating, the main breaker, the busbar, the outgoing ways for host, mixer, palletizer, feeder, compressor and lighting, the changeover to the generator, and the earth arrangement. A cable schedule with sizes and route lengths. A cabinet position away from the mix charging area, and a generator room with ventilation and exhaust away from the curing area.
Send the model mix you plan to run, the shift pattern and the site voltage through the contact page, and the load table, the transformer step and the generator rating follow from them. The maintenance side of the same plant is on the maintenance and spares page, and the consumption side of the machine itself is in the electricity consumption guide. The electrical design is cheap to change on paper and expensive to change after the foundation.
Frequently Asked Questions
How much power does a block making plant need?
What size transformer does a block plant require?
What size generator does a block plant need?
Why does the site voltage matter before the machine is built?
How is the electricity cost of a block factory calculated?
Can a block plant run on a generator alone?
Related machines

Concrete Block Making Machine
Core machine for hollow blocks, solid blocks, pavers and curbstones.

Automatic Block Making Machine
High-output automatic block machine for industrial production lines.

Hydraulic Block Making Machine
Hydraulic forming system for stable density and consistent blocks.

Hollow Block Making Machine
Machine configurations for common hollow concrete block sizes.