Power Supply for a Block Plant: Connected Load and Generator Sizing

Connected load, current and kVA for each host and mixer, transformer and generator sizing, why the site voltage is fixed at order stage, and the protection a block plant needs.

QUICK ANSWER

A block plant is sized on two numbers: connected load and the largest motor start. A QST8-15 with a JS750 mixer, pallet feeder and QS-1200A palletizer reaches about 120 kW, roughly 214 A at 380 V and 141 kVA, so the transformer step is 160 or 200 kVA. The generator needs about 25 percent headroom above running load and must accept the mixer starting at six to seven times full load current.

A block plant is designed twice. First as a layout, which everyone discusses, and then as an electrical single line diagram, which usually gets settled late, by whoever is wiring the site. The second drawing decides whether the line starts on the day the installation team arrives, or waits three weeks for a transformer that was ordered after the foundation was poured.

Two numbers carry the whole decision: the connected load of everything that runs at the same time, and the starting current of the largest motor. The first sizes the transformer and the cable, the second sizes the generator.

How much power does a block plant need?

The connected load is the sum of the host machine, the mixer, the pallet handling equipment and the conveyors, plus lighting, a compressor and a water pump. Most buyers know the figure for the host and forget that the mixer can draw as much as the press.

Installed capacity is published per model, and it is the number to add up rather than a family average:

Host modelInstalled capacityNote
QT4-1522.9 kWCompact automatic host, 25 MPa forming pressure
QST6-1534.4 kWPlus 3.0 kW for the stacking machine
QT5-1537.4 kW25 MPa, 1,100 x 650 x 20 mm pallet
QSMT100039.5 kW or 57.5 kWTwo sizes in the pallet-free series
QST8-1544.9 kWPlus 3.0 kW for the stacking machine, 31.5 MPa
QS600 static press46.9 kW31.5 MPa, 850 x 700 mm forming area
QS800 unidirectional54.9 kW31.5 MPa, 1,100 x 680 mm forming area
QS1000 unidirectional66.4 kW31.5 MPa, 1,100 x 850 mm forming area
QS800 bidirectional70 kW31.5 MPa, 18 to 22 s cycle
QS1500 unidirectional88.4 kW31.5 MPa, 1,440 x 850 mm forming area
QS1000 bidirectional105.4 kW31.5 MPa, 600 mm main cylinder bore
QS1500 bidirectional108.2 kW31.5 MPa, 43 t machine weight
QST1200, QST1500, QST1800From the drawingPublished specifications give size and pallet, not installed capacity

Then the equipment around the host, which is where a load calculation usually goes wrong:

ItemInstalled capacityWhen it runs
QS-1200 automatic pallet feeder3 kWContinuously, 13 s per feeding cycle
QS-1200A low position palletizer29.5 kWContinuously during packing, 18 s per layer
JS500 twin shaft mixer25.5 kWBatch cycles, 25 m3 per hour
JS750 twin shaft mixer39.35 kWBatch cycles, 35 m3 per hour
JS1000 twin shaft mixer50.2 kWBatch cycles, 50 m3 per hour
JS1500 twin shaft mixer75 kWBatch cycles, 75 m3 per hour
Conveyors, compressor, lighting, pumpAdd from the site drawingMixed, and never zero

Two worked examples show how far apart a small and a large line sit. A QST8-15 with a JS750 mixer, a pallet feeder and a QS-1200A palletizer adds up to 44.9 + 3.0 + 39.35 + 3.0 + 29.5 = 119.75 kW, so about 120 kW before lighting and a compressor. A QST6-15 with a JS500 mixer and a pallet feeder, without a palletizer, is 34.4 + 3.0 + 25.5 + 3.0 = 65.9 kW. A QS1000 bidirectional press with a JS1000 mixer, feeder and palletizer reaches 105.4 + 50.2 + 3.0 + 29.5 = 188.1 kW.

How do you turn kilowatts into amps, kVA and a transformer size?

Current on a three phase supply follows the load, the voltage and the power factor:

Amps = watts divided by 1.732 x 380 x power factor. With a power factor of 0.85, the 120 kW line draws about 214 A, the 66 kW line about 118 A, and the 188 kW line about 336 A.

Apparent power is kilowatts divided by the same power factor, so 120 kW needs roughly 141 kVA of transformer capacity. Choose the next standard size above that figure and leave room for the load you will add later, which in practice means a 160 kVA or 200 kVA unit for a single 120 kW line. The utility connection application is the slowest item in the whole project, so the figure is needed months before the machine ships.

Line exampleConnected loadCurrent at 380 V, 0.85 PFApparent powerTransformer step to plan
QST6-15, JS500, feeder65.9 kW118 A78 kVA100 kVA
QST8-15, JS750, feeder, QS-1200A119.75 kW214 A141 kVA160 kVA or 200 kVA
QS1000 bidirectional, JS1000, feeder, QS-1200A188.1 kW336 A221 kVA250 kVA

Those figures are starting points, not a utility submission. A real calculation uses the actual site voltage, the power factor of the motors supplied, the cable route length and the derating for a hot cabinet. What the table does is fix the order of magnitude early enough that the transformer is not the reason a finished line sits idle.

How big should the generator be?

Bigger than the running load, and sized on the worst starting event rather than on the total. The mixer is usually the largest single motor on a block line, at 39.35 kW on a JS750, and a direct on line start pulls six to seven times its full load current for a few seconds. A generator that matches the running load exactly will drop on that start, and the press control will reset in the middle of a cycle.

The working rule is a continuous rating above the running load with 25 percent headroom, so 120 kW lands at 150 kVA minimum and about 200 kVA with the margin, and the alternator datasheet is then checked for the transient the mixer demands. Below roughly 40 percent of its rating a diesel generator runs cold and wet stacks, so oversizing by two steps costs fuel and engine life as well as money.

Changeover between the utility and the generator needs a mechanically interlocked switch, never a manual plug, and the generator needs its own earth. On a site where the utility drops several times a day, the generator also has to carry the hydraulic power unit while the press is holding pressure, which is the moment a soft supply shows up as a drifting cycle.

Why does the site voltage have to be settled before the order?

Because motors, contactors, the control transformer and any drive on the machine are built for one voltage and one frequency. Machines for this region are configured for 380 V, 50 Hz, three phase supply, and that is stated on the product pages for the block, hollow block and hydraulic press ranges. A site supplied at 415 V or at 60 Hz is a different machine build, not a switch setting.

So the order stage collects four answers: voltage, frequency, number of phases, and whether the plant will run on the utility, a generator, or both. Getting one of them wrong after the machine has shipped means rewinding motors or replacing contactors on site, with the line stopped while it happens.

What protects the line when the supply is unstable?

A phase failure and phase sequence relay first, because a lost phase stops one motor and burns another, and voltage sags are common on the networks that feed industrial zones in the region. Then an under and over voltage relay, a surge arrestor at the incoming panel, and a voltage stabiliser where the utility swings widely through the day.

Inside the plant, the control cabinet needs filtered fan cooling rather than an open door, because a block plant makes dust all day and a dusty drive fails in the hottest week of the year. Cable sizing follows the starting current and the route length, not the running current, and the earth electrode is separate from the neutral bond at the transformer.

How do you estimate the electricity bill?

Multiply connected load by a load factor and by the hours the plant runs, then by the local tariff:

kWh per month = connected kW x load factor x hours per month. The load factor is well below one, because the mixer batches, the press ramps between filling, pressing and ejecting, and the palletizer works in cycles. Until a meter has recorded a month, a range of 0.5 to 0.7 of connected load is a reasonable planning figure for a line in production.

Two habits bring the figure down without touching the machine. Power factor correction at the incoming panel reduces the reactive charge that many utilities bill separately, and shifting the heaviest production into the hours when the tariff is lower, where such a tariff exists, moves consumption without reducing output.

What belongs on the electrical drawing before construction?

A single line diagram with the transformer rating, the main breaker, the busbar, the outgoing ways for host, mixer, palletizer, feeder, compressor and lighting, the changeover to the generator, and the earth arrangement. A cable schedule with sizes and route lengths. A cabinet position away from the mix charging area, and a generator room with ventilation and exhaust away from the curing area.

Send the model mix you plan to run, the shift pattern and the site voltage through the contact page, and the load table, the transformer step and the generator rating follow from them. The maintenance side of the same plant is on the maintenance and spares page, and the consumption side of the machine itself is in the electricity consumption guide. The electrical design is cheap to change on paper and expensive to change after the foundation.

FAQ

Frequently Asked Questions

How much power does a block making plant need?
It depends on the host and the mixer together. A QST6-15 host at 34.4 kW with a JS500 mixer at 25.5 kW and a 3 kW pallet feeder is about 66 kW connected. A QST8-15 at 44.9 kW with a JS750 mixer at 39.35 kW, a feeder and a QS-1200A palletizer at 29.5 kW reaches about 120 kW before lighting.
What size transformer does a block plant require?
Size on apparent power, which is connected kilowatts divided by the power factor. A 120 kW line at a power factor of 0.85 needs about 141 kVA, so the next standard steps are 160 kVA or 200 kVA. Add the lighting, compressor and pump load, then leave one spare outgoing way for the second machine or the second shift you plan later.
What size generator does a block plant need?
A continuous rating above the running load with about 25 percent headroom, then checked against the largest motor start. For a 120 kW line that means 150 kVA minimum and roughly 200 kVA with margin, and the alternator must accept the mixer starting at six to seven times full load current. Running a generator below 40 percent of rating causes wet stacking.
Why does the site voltage matter before the machine is built?
Because motors, contactors, the control transformer and any drive are built for one voltage and one frequency. Machines for this region are configured for 380 V, 50 Hz, three phase. A site at 415 V or 60 Hz needs a different build, and changing it after shipping means rewinding motors or replacing components on site with the line stopped.
How is the electricity cost of a block factory calculated?
Connected kilowatts multiplied by a load factor, by the running hours and by the local tariff. The load factor is below one because the mixer batches and the press ramps between filling, pressing and ejecting, so 0.5 to 0.7 of connected load is a reasonable planning range until a meter has recorded a full month on the line.
Can a block plant run on a generator alone?
Yes, and many sites in the region do, but the generator is then sized on the starting current of the mixer rather than on the running load, and fuel becomes a production cost per block. A hybrid arrangement with a utility connection and a generator on interlocked changeover is usually cheaper to run than generation alone, and it keeps the press running through a voltage dip.