Block Supply Agreement: The Clauses That Protect the Plant

A block supply agreement is judged a year later, on the clauses that were left out. These are the ten that decide who pays when the blocks, the dates or the cement price move.

QUICK ANSWER

A block supply agreement is the written contract between a plant and a project buyer: which block class, how much per month, at what price basis, tested how, delivered where and paid when. It should fix a volume band rather than a single figure, a price that can be adjusted when cement moves, a sampling and acceptance procedure, a delivery window with a waiting rule, a capped delay penalty and a payment security. Ten clauses carry the risk, and every one of them is cheaper to settle before the first truck than after the first rejection.

What is a block supply agreement and when does a plant need one?

A block supply agreement is the document that turns a series of orders into one arrangement: a named buyer, a product class, a volume band for a period, a price basis, and the procedure that decides whether a delivery is accepted. It sits above the individual call-off, which only states a quantity and a date inside the terms already agreed.

It is not the same thing as a quotation, and it is not the same thing as a dealer agreement. A quotation prices one load. A dealer agreement sets up resale in a territory. The supply agreement prices a relationship, and it is needed whenever a buyer wants a price held for months, a volume reserved, or a specification honoured across many deliveries.

The moment a consultant writes the block specification into the project documents, the plant also needs one, because from that day the acceptance standard is no longer the plant's own opinion. Everything a delivery will be judged on has to be agreed in writing before the first load leaves the yard.

What must a block supply agreement fix in writing?

Ten clauses, and the table shows what each one protects against. A contract that names nine of them and leaves one open will be argued about on the tenth.

ClauseWhat it must stateWhat goes wrong without it
Parties and sitesLegal names of buyer and plant, delivery sites, who may sign a call-offBlocks delivered to a site nobody contracted for, and nobody pays
Product specificationClass, dimensions, tolerance, finish, and the approved reference sampleQuality disputes settled by opinion at the gate
VolumeMonthly band, take-or-pay share, call-off notice periodThe plant reserves capacity for volume that never arrives
Price basisPer block or per load, ex yard or delivered, what is included, tax treatmentA freight argument on every delivery
Price adjustmentCement reference, threshold, pass-through share, frequency, evidenceSix months of margin eaten by one cement movement
Sampling and acceptanceSample approval before the first load, test frequency, who pays, rejection windowEvery delivery argued, and blocks rejected after they are laid
DeliveryWindow from call-off, unloading duty and equipment, waiting time, split loadsThe plant blamed for a site that cannot unload in an hour
PaymentTerms, certificates, retention, security, stop-supply rightThe plant finances the project without saying so
Delay penaltyRate per day, cap, and the remedy the plant may chooseUnlimited exposure for a week of rain or a power cut
Termination and force majeureNotice, defined events, and what is paid on exitCured stock and dedicated moulds stranded when the job stops

Two of these deserve their own negotiation because they decide the money: the volume clause and the price adjustment. The others are standard drafting, provided they are actually drafted.

How should the volume clause be written?

As a band with a floor, not as one figure. A monthly minimum the buyer must take or pay for, a monthly maximum the plant is obliged to supply, and a call-off notice period in days. The floor is what allows the plant to reserve cement, pallets and a shift. The ceiling is what protects the plant from a single buyer who wants half its output and then leaves.

The band has to be checked against the line, not against the buyer's programme. A QST6-15 forms 8,640 to 11,520 hollow blocks in an eight hour shift, and the real constraint on a committed volume is often the cure pipeline rather than the machine: a block sits on its pallet for twenty to twenty four hours and needs about seven days damp before it travels, so a plant promising a steady weekly delivery is really promising a week of production standing in the yard. Write the band, then check that the yard can hold the stock it implies.

How is the price written when cement moves?

Start with the basis, in words that cannot drift: per block or per cubic metre, ex yard or delivered to a named site, and whether tax is included. Then add a reference for the one input that moves most. Cement is the largest purchased line in the variable cost of a block even though it is only about a tenth of the mass, so a contract that fixes the price for six months is a bet on that one line.

A workable adjustment clause names the reference (a supplier's published price per tonne, or a quotation the buyer may verify), a threshold below which nothing changes, the share of the movement that passes through, the frequency of review, and the evidence required. It also states that adjustment applies to loads not yet delivered and never retroactively. How much a given move costs the plant is arithmetic rather than negotiation, and it is worked through on the currency and inflation page.

What does the acceptance procedure have to say?

Five things. When the reference sample is approved, and that it is dated, marked and held by both parties. How a delivery is traced to production, which means batch records the plant can produce on request. How often compressive testing is done, on whose samples, and at which laboratory. Who pays for a failed test, which is normally the plant, against the buyer paying for a pass. And the rejection window, with the rule that blocks already laid are not returnable and are dealt with as a price remedy instead.

Write the rejection remedy as replacement first, credit note second. A replacement costs the plant one more load. A credit note on blocks that have already been built into a wall costs the load and the wall.

Which delivery terms keep the plant out of trouble?

The delivery window counted in days from a written call-off, not from a phone conversation. The unloading duty stated plainly: whose equipment, whose labour, and how long a truck may stand before a waiting charge applies. Whether split deliveries are allowed and who pays the extra trip. The notice the plant gives before dispatch, and the site hours it can actually deliver in.

A block plant that loads its own trucks is exposed at both ends of the trip. On a project with restricted access, a single unloading delay can take a truck out of the day and push two other deliveries. The waiting rule is not hostility. It is the only way to keep a promise to the next buyer.

How are penalties and remedies written?

A delay penalty per day, calculated on the value of the delayed portion, with a cap expressed as a percentage of the contract value and a stated remedy the plant may choose instead: replacement, price reduction, or delivery at the plant's cost. What must not appear is unlimited liability or an open commitment to consequential loss, because a week of blocked site access can otherwise cost more than the year's margin.

Force majeure has to be defined rather than assumed. Rain that stops laying, a power cut that stops forming, a cement shortage that stops supply, and a security event that closes a road are four different things, and each one needs a stated consequence: extension of the delivery window, suspension, or termination without penalty. Writing them down is what keeps a routine interruption from becoming a dispute.

What payment security is normal for block supply?

What the plant can actually enforce: an advance or a deposit on the first order, payment against delivery for cash buyers, payment against certificate for project buyers, and a retention that is released on a stated date rather than on a handover nobody controls. Beyond that, security instruments belong to the jurisdiction, and the shape of them is a question for a local lawyer rather than for a supplier.

Two rights are worth more than any instrument. The right to stop supply when an invoice passes a stated overdue limit, written into the agreement so that stopping is not a breach. And retention of title until the blocks are paid for, which in practice is only useful while the blocks are still in the yard, and that limits how much credit a plant should extend to a buyer who takes delivery weekly.

Which clauses fail most often in practice?

Five, and they fail in the same way: they are written loosely enough to be argued. A specification that names a block by trade name, such as a twenty centimetre block, without a class and a tolerance. A delivery window with no waiting rule, so the plant absorbs every site delay. A price with no adjustment clause in a contract that runs through a cement movement. Acceptance by opinion, with no approved sample and no test frequency. And call-offs taken verbally, which leaves the plant holding stock for a quantity nobody admits to ordering.

Each of those is a one paragraph fix at signature and an expensive argument eighteen months later. That asymmetry is the whole reason to spend an hour on the document before the first truck.

What should the plant check before it signs?

Capacity first, in the plant's own numbers: shifts available, blocks per shift, and the cured stock the yard can hold. Then the inputs the volume depends on, which are cement cover for the committed tonnage, moulds for each class in the agreement, and pallets. A QST6-15 line keeps roughly 1,440 pallets in circulation per shift, and 1,000 hollow blocks occupy about 167 pallet loads, so a large committed volume is a pallet commitment as much as a machine commitment.

Then the paperwork: the laboratory that will test, the batch record the plant can actually produce, and the appendix that carries the price basis, the band, the window and the retention in one page. If the plant cannot produce the documents the agreement calls for on day one, the agreement is premature, however good the price is.

An agreement is not a way to win a buyer. It is the way to keep a buyer without carrying his risk, and the clauses that do that are the ones nobody enjoys discussing at the start.

Keep reading with how to sell concrete blocks, quality control in a block plant, block delivery lead time and order priority, currency and inflation risk, cement and aggregate supply contracts, block reject rate and waste, payment terms for a block production line and working capital for a block factory.

FAQ

Frequently Asked Questions

What is the difference between a supply agreement and a purchase order?
A purchase order states a quantity, a price and a date for one delivery. A supply agreement sets the terms that all the purchase orders sit inside: the class of block, the volume band, the price basis and its adjustment, the acceptance procedure and the payment security. A plant that works only on purchase orders renegotiates its risk on every load, and loses those arguments after the blocks are on site.
How long should a block supply agreement run?
Long enough to justify reserving capacity, short enough to reprice before the terms go stale. Three to six months suits most project supply, and twelve months is workable only with a cement adjustment clause and a review date. An agreement with no end date and a fixed price transfers every future cost movement to the plant, which is the one risk the plant cannot absorb quietly.
Should the block price be fixed for the whole contract?
Only if the contract is short or the buyer accepts a price that already carries the risk. Cement is the largest variable line in a block, so a fixed price over a long period is a wager on that single input. The usual answer is a base price plus a cement adjustment with a threshold, a pass-through share and a review date, which keeps the price firm in normal weeks and honest in a spike.
Who pays for a failed compressive test on delivered blocks?
The plant, when the failure is real, and the buyer when the sample was mishandled or taken from the wrong batch. The clause should say which laboratory, whose samples, what frequency and what evidence both sides keep. Paying for a failed test is cheap compared with replacing blocks already laid, which is why the acceptance procedure matters more than the test invoice.
Can the plant charge for waiting time at a site?
Yes, if the waiting rule is in the agreement before the first delivery. State how long a truck may stand after arrival, what the charge is per hour beyond that, and who signs the ticket. Without the rule, the plant absorbs every site delay and the cost appears as an unexplained gap between the quoted price and the cash collected at the end of the month.
What retention is normal on block supply?
Retention of five to ten percent held for the duration of the works is common on project supply, and the clause has to name the release event and the date. Retention is the buyer's security, not a discount, so it belongs in the price calculation from the start. A plant that discovers retention after the first invoice has priced the contract without the cost of holding that money.
How should volume be written when the buyer will not commit?
Use a floor and a ceiling with a take-or-pay share on the floor, and price the reservation. A buyer who wants capacity held but will not commit volume should either pay a reservation charge or accept a higher unit price for the first tranche. Offering an uncommitted band and a discount at the same time is how a plant ends up holding stock and cement for a programme that was never firm.
What happens if cement prices rise in the middle of a contract?
Nothing, unless the agreement has an adjustment clause, which is why that clause is worth more than the discount negotiated at signature. The clause names the reference price, the threshold that triggers a review, the share of the movement that passes through to the buyer, the review frequency and the evidence. Loads already delivered stay at the price agreed for them, with no retroactive adjustment.