Fuel Storage for a Block Plant: Tank Size and Safety
Diesel storage is sized by how often a tanker can reach the site, not by the engine on the canopy. Here is how litres per shift become a tank size, where the tank stands, and how the fuel stays clean and countable.
Fuel storage for a block plant is sized from litres per day multiplied by the days between deliveries, plus two or three days of reserve. A line drawing 92.4 kW burns about 114 litres in an eight hour shift at a load factor of 0.7 and 0.22 litres per kWh, so two shifts come to roughly 230 litres a day and a weekly delivery needs a tank near 1,600 litres. Tank size follows the delivery cycle and not the generator rating, and the bund, the water separator and the daily log decide whether that fuel reaches the engine clean.
How much fuel storage does a block plant need?
Fuel storage for a block plant is a delivery question before it is an engineering question. The tank is not sized to the generator rating on the canopy. It is sized to the number of days the plant can run between two tanker deliveries, with a reserve for the week when the road is closed, the supplier is out of stock or the site is working two shifts instead of one.
Three numbers produce the size. The first is litres per day, which comes from the connected load and the hours the line actually runs. The second is the delivery interval the local fuel supplier can hold, which in most of the region is weekly for a small plant and fortnightly or monthly for a larger site that can take a full tanker. The third is the reserve, which should not be less than two days and is better at three, because a plant that stops for fuel stops for a day and pays the crew for it.
The formula is short enough to write on the tank itself: tank litres equals daily litres multiplied by the days between deliveries, plus the reserve days. Everything else on this page is about making those litres arrive in the engine without water, without loss and without an argument at the end of the month.
How many litres does one shift burn?
Start from the connected load of the line that will actually be installed, then correct it with a load factor. A compact automatic line of the QST6-15 type adds the host press at 34.4 kW, a JS500 twin shaft mixer at 25.5 kW, a pallet feeder at 3 kW and a palletizer at 29.5 kW, which is 92.4 kW connected. A QST1500 line with a JS1000 mixer reaches 151.8 kW on the same arithmetic, and a QST1800 line with a JS1500 mixer reaches 211.5 kW.
Diesel consumption then follows the load factor and the specific consumption of the set. At a load factor of 0.7 and 0.22 litres per kWh, which is a healthy set running in its upper half, the shift figures fall into the band below. The second column is the pessimistic case at 0.25 litres per kWh, and a real site will land somewhere in between until a meter and an hour meter replace the estimate.
| Line | Connected load | Litres in an 8 hour shift at 0.22 L per kWh | At 0.25 L per kWh | Two shifts per day |
|---|---|---|---|---|
| QST6-15 host, JS500 mixer, feeder, palletizer | 92.4 kW | 114 | 129 | 228 to 259 |
| QST8-15 host, JS750 mixer, feeder, palletizer | 116.8 kW | 144 | 164 | 288 to 327 |
| QST1500 host, JS1000 mixer, feeder, palletizer | 151.8 kW | 187 | 213 | 374 to 425 |
| QST1800 host, JS1500 mixer, feeder, palletizer | 211.5 kW | 261 | 296 | 521 to 592 |
Read the table as a planning band, not as a promise. A line that waits between batches draws less. A line with a leaking hose on the compressor, a conveyor left running through the break or a yard lit all night draws more, and those are the losses a tank size cannot fix.
How do you turn daily litres into a tank size?
Multiply by the delivery interval and add the reserve. The table below does that for the smallest and the largest line in the range, on two shifts, so the difference between a weekly and a monthly delivery is visible before the tank is ordered. A monthly tank on a two shift QST1800 site is a 16,000 litre installation, which is a different civil job and a different fire risk from a 4,000 litre drum-fed tank.
| Delivery interval | Tank for a 92.4 kW line, two shifts (228 L per day) | Tank for a 211.5 kW line, two shifts (521 L per day) |
|---|---|---|
| Weekly, plus 2 days reserve | about 2,050 litres | about 4,700 litres |
| Every two weeks, plus 2 days reserve | about 3,650 litres | about 8,350 litres |
| Monthly, plus 2 days reserve | about 7,300 litres | about 16,700 litres |
Two practical limits push the answer back down. Fuel bought is cash spent and it sits in a tank instead of in the business, so a monthly tank is also a monthly loan to the fuel supplier. Diesel also ages: in a hot climate, a tank that is filled once a month holds fuel at the far end of its useful life by the time it is burned. For most plants between 2,000 and 6,000 litres is the sensible range, and anything above that should be justified by a road that is genuinely closed for weeks, not by a wish to avoid phone calls.
Do you need a bulk tank, a day tank, or both?
Most generator sets arrive with a small tank inside the canopy that holds a few hours of running. That tank is a day tank, not storage, and refilling it by hand from drums is how fuel gets spilled on the slab and miscounted in the log. The clean arrangement is a bulk tank at ground level, a transfer pump with a meter, and a day tank or a direct line to the set that is filled once a shift.
A day tank at the set also settles the fuel pressure question on a long run: the engine draws from a small vessel that is always full, instead of pulling fuel through thirty metres of pipe and a filter with a partial vacuum. Where the bulk tank stands far from the generator, size the transfer line for the refill rate the engine needs, not for the average daily consumption.
Where should the tank stand?
Outside the production hall, on a concrete plinth, inside a bund that holds at least 110 percent of the tank volume. The fill point belongs inside the bund as well, because most spills happen at the fill connection and not at the tank shell. There should be no yard drain and no rainwater outlet inside the bund, otherwise the first heavy rain carries a film of diesel across the yard and the bund becomes a decoration.
Distance from the hall, the cement silo and any hot work is set by the local civil defence or fire authority, and that number should arrive in writing before the plinth is cast. What is certain everywhere is that the tank is not inside the production building, not under a roof that collects heat, and not beside the welding bay where a mould gets repaired. A fence, a locked cap and a visible level gauge finish the installation.
What does a hot climate do to stored diesel?
Heat does three things to fuel and all three end up in the injection pump. Day and night temperature swing pulls moist air in and out of the tank through the vent, and the water condenses on the inside of the shell and settles at the bottom. Warm fuel oxidises faster and darkens, and water at the bottom of a tank is where microbial growth starts, which arrives as a black slime on the filters.
The countermeasures are cheap and weekly. Keep the tank shaded or bury it in a bund wall that shades the shell, keep it as full as the delivery interval allows so there is less air to breathe in and out, drain the sump at the bottom for a few seconds every week and look at what comes out, and change the water separator filter on the interval in the genset manual rather than when the engine stumbles. Fuel that has sat for six months in a hot yard is not the fuel the set was tuned for.
Which fittings belong between the tank and the engine?
The chain is short and every item on it earns its place. A coarse strainer at the fill stops the grit that comes with a roadside delivery. A water separator and primary filter before the transfer pump catches the water the sump drain misses. A non-return valve keeps the line charged, an isolation valve inside the bund lets the tank be closed off without emptying the yard, and a mechanical level gauge plus a dipstick give two independent readings that can be compared.
Bonding and earthing belong on the same drawing, because fuel moving through a pipe generates static and a plastic tank on a dry slab has nowhere to put it. The transfer pump should carry a meter, not only a switch: the meter is what turns a morning of refuelling into a number that can be compared with the engine hour meter at the end of the month.
How do you keep fuel from disappearing?
Fuel is the one consumable on a block plant that leaves no visible trace. Blocks can be counted, cement is delivered by weight, but diesel evaporates, leaks and occasionally walks. Three numbers written by the same person at the same hour every day catch all three: litres delivered into the tank, hours on the engine hour meter, and blocks produced in the shift.
Litres divided by blocks is the only figure worth arguing about, and it should be reviewed weekly against the fuel invoice rather than monthly. Litres rising while block count is flat points to a new load, a blocked filter, an injector passing fuel or a tank being drawn by someone else. Litres flat while block count falls points to idle running, which is the most common fuel loss in a plant that reports a good shift on paper. A locked cap with one key holder, and a dip taken before and after every delivery, close the rest.
What fire and spill provisions are non-negotiable?
A dry powder extinguisher at the tank and another at the generator, a no smoking sign at the fill point, a spill kit with absorbent, a drip tray under the transfer pump, and a procedure that the crew has actually practiced once. Welding, grinding and cutting within the bund are forbidden, and that rule has to survive the day a mechanic decides to repair a pallet frame next to the tank because it is the flat piece of concrete on site.
The bund needs an emptying rule as well. Water that collects inside it must be removed by hand or with a separator, never by opening a drain valve into the yard soil, and the absorbent used on a spill belongs in a closed drum, not in the general waste behind the curing area.
What belongs on the drawing and in the fuel log?
The site drawing should show the tank, the bund, the fill point, the pipe route, the isolation valve, the earth connection and the extinguisher positions, with the fire authority distance written on it. That drawing is what a new electrician or a visiting inspector reads, and it is the only record that the installation was designed rather than assembled.
The log is a single sheet with a fixed header: date, litres delivered, dip before, dip after, engine hours, blocks produced, and the initials of the person who did it. One sheet per month, kept with the fuel invoices, converts the tank from a cost into a measured input, and it is the first document a buyer should ask to see when a plant is offered for sale as a going concern.
What should the fuel plan contain before the line is ordered?
Five lines are enough at the quotation stage: daily litres on one shift and on two, the delivery interval the supplier can hold, the tank size that follows from both, the bund and distance the local fire authority requires, and the name of the person who owns the log. A plan that answers those five questions prevents the most expensive version of this problem, which is a plant that is complete, connected and waiting for a tanker while the crew stands in the yard.
Keep going with generator fuel cost per block, power supply and generator sizing, block plant safety, block plant shutdown and restart and working capital for a block factory.
Frequently Asked Questions
How big should the diesel tank be for a block plant?
How many litres of diesel does a block plant burn per shift?
Is it cheaper to run a block plant on diesel or on the grid?
How often should the fuel tank sump be drained?
Does a block plant need a bund around the fuel tank?
How do you stop diesel theft at a block plant?
Can diesel be stored for several months in a hot climate?
Which figures belong in the fuel plan for a new block plant?
Related machines

Concrete Block Making Machine
Core machine for hollow blocks, solid blocks, pavers and curbstones.

Automatic Block Making Machine
High-output automatic block machine for industrial production lines.

Hydraulic Block Making Machine
Hydraulic forming system for stable density and consistent blocks.

Hollow Block Making Machine
Machine configurations for common hollow concrete block sizes.