Shift Handover Records and Crew Performance in a Block Plant

A one page handover sheet and five reconciled numbers decide whether a block plant can explain its own output. This page sets the fields, the arithmetic and the incentives.

QUICK ANSWER

A shift handover record for a block plant is a one page sheet that passes from the outgoing crew to the incoming one and carries the same fields every shift: blocks formed, pallets filled, rejects, stoppage minutes by cause, the mould fitted, material on hand, pressure and oil temperature, open faults, and the checks the next supervisor must make in person. It earns its place only when blocks are reconciled against pallets, because an output figure nobody cross checks is the first number to drift in a plant that looks busy.

A block plant can run a full shift, fill the curing yard and still be unable to say what it produced. The machine counted cycles, the forklift moved pallets, the yard filled, and by the time the second shift arrived nobody could say whether the last eight hours had been good or merely busy. That gap is not a machine fault. It is the absence of a shift handover record, and on a two shift plant it is the most expensive sheet of paper the plant does not have.

What makes the record worth keeping is not the writing. It is the reconciliation: blocks formed against pallets filled, pallets filled against curing places, rejects against the mould that is fitted. A plant that closes those three numbers every shift finds within a week which post is drifting and which stoppage keeps repeating. The maintenance schedule on this site covers what is inspected on the machine. This page covers the sheet the crew hands over, and the crew performance numbers that make the sheet worth reading.

Why does a block plant need shift handover records at all?

Because the output is produced by a crew that changes, on a machine that does not. Every shift opens with a fresh set of assumptions: how fast the line is really running, which mould is in the machine and how many cycles it has done, how much cement sits in the silo, which alarm was cleared an hour ago and whether it is coming back. Without a written handover those assumptions are rebuilt from memory every eight hours, and memory politely improves.

The cost appears as a slow drift rather than a breakdown. Output falls from 9,600 blocks to 8,900, nobody can say on which shift the drop started, and the sales side quietly shortens its promises. A handover record converts that drift into a number with a date against it, which is the only form in which a plant can act on it.

There is a second reason, harder to price. A block line is a chain of posts, and on an automatic plant there are only three to six people on it per shift, or three to four workers per line on a mother and child vehicle curing system. With a crew that small, one post that nobody owns is enough to lose a shift. The handover sheet names the owner of every open item, so the incoming crew inherits tasks instead of inheriting a rumour. The post list itself is set out in operator training for block production.

What belongs in the shift handover records of a block plant?

Ten fields, one page, filled in by the shift supervisor before the crew leaves the floor. Nothing on the list requires software, and nothing on it takes more than ten minutes to write if the numbers are already being counted at the machine.

FieldWhat is writtenWhy it is on the sheet
Cycles and blocks formedCounter reading at start and end of shift, blocks per mould, total blocksThe only output figure that cannot be inflated by opinion
Pallets filledPallets sent to curing, with a count per product typeCross checks the block total and drives the curing pipeline
RejectsCount and reason, wet rejects separated from cured rejectsWet rejects point at the mix or the mould, cured rejects at handling
Stoppage minutes by causeMinutes against a fixed list of cause codesTurns complaints into a summable number
Mould in the machineProduct, mould number, cycles accumulated on that setDecides when the mould comes out for measurement
Cement and aggregate on handTonnes in the silo and stockpile at handoverPrevents the incoming shift discovering an empty silo at 02:00
Pressure and oil temperatureGauge reading against the rated pressure of the model, oil temperature at handoverEarliest warning of a pump, seal or relief valve problem
Open faultsAlarm shown, action taken, whether it was cleared or bypassedA bypassed safety or position sensor is a debt, not a repair
Curing yard stateEntries by date, pallets due out tomorrow, places freeLinks today's forming to the delivery note three days later
Physical checks for the incoming crewThree to five items the next supervisor must look at personallyWritten items get checked, verbal ones do not

How do you reconcile shift output with the pallets that left the line?

Multiply, then compare. A QST6-15 forms six 390 x 190 x 190 mm hollow blocks per cycle, and its forming cycle runs from 15 to 23 seconds. At 15 seconds that is 1,920 cycles in an eight hour shift, or 11,520 blocks. At 20 seconds it is 1,440 cycles and 8,640 blocks. At 23 seconds it is 1,252 cycles and 7,512 blocks. The same arithmetic gives the pallet count, because each cycle fills one pallet position of 980 x 680 x 20 mm, so a full shift consumes roughly the same number of pallets as cycles.

Two independent counters then have to agree. If the PLC shows 1,410 cycles and the pallet log shows 1,390 pallets, the eighteen pallet gap is either a double count at the magazine or pallets pulled off the line for repair, and both are worth a sentence on the sheet. If the PLC shows 1,410 cycles and the pallet log shows 1,150, somebody is counting pallets that never left the machine, which usually means the log is filled in from memory at the end of the shift.

On a static press line the same logic uses a different pair. A QS1000 unidirectional press runs an 18 to 22 second cycle with a 1,100 x 850 mm forming area on a 1,200 x 900 x 20 mm pallet, so the count of cycles per shift is low and the count of pieces per cycle is high. Reconcile pieces against pallets there, not cycles against pallets, or the sheet will show a permanent phantom shortfall.

Which crew performance numbers are worth writing down every day?

Five, and no more. A sheet that asks for fifteen numbers gets three of them filled in properly. These five are the ones that can be acted on the following morning.

NumberHow it is computedWhat it exposes
Blocks per shift, reconciledPallets filled multiplied by blocks per mould, compared with the counterReal capacity against the figure the plant was sold
Reject share of the shiftRejects divided by blocks formed, wet and cured counted apartMix or mould problems before they reach a customer
Unplanned stoppage minutesSum of cause codes excluding planned maintenance and mould changesWhether the line is losing time to equipment, material or organisation
Mould change minutesClock time from last block of the old product to first good block of the new oneThe true cost of a product switch, which is usually half a shift
Pallets brokenPallets removed from the circuit, counted at the yardHandling quality and the pallet buffer actually needed

The five are deliberately chosen so that none of them can be improved by hiding a fact. A crew cannot raise reconciled blocks without filling pallets, cannot lower stoppage minutes without naming a cause, and cannot reduce broken pallets by leaving them in the stack.

How should stoppage time be coded?

Against a closed list of nine codes: no cement or aggregate, no pallets, mould change, mechanical, hydraulic, electrical and control, quality hold, yard or truck full, and power. Nine is enough for a block plant and small enough that a supervisor remembers them without a card. Every stoppage gets one code and one number of minutes. Free text is forbidden on that line, not because supervisors write badly, but because free text cannot be added up at the end of the month.

The first monthly total usually settles an argument that has been running since commissioning. A plant convinced it loses time to hydraulics often finds the largest line is pallets, and the fix is a buffer and a repair bench rather than a service engineer. Coding the stops is also how a maintenance schedule improves: a code that appears three times in a week is a work order, and a code that appears once a month is a note.

What does a two shift plant need that a one shift plant does not?

A physical handover at the machine, not a sheet left on a desk. The incoming supervisor reads the page and then walks five things: the pressure gauge against the rated pressure of the model, which is 25 MPa on a QST6-15 or a QT4-15, 31.5 MPa on a QST8-15 and across the static press range, and 21 MPa on a QSMT1000 pallet free machine; oil level and temperature; the mould actually fitted and its condition at the edges; the pallet magazine and the top of the stack in the yard; and the silo level against the tonnage written on the sheet.

The walk takes ten minutes and it is not a formality. At a night handover the incoming crew is the only check on what the outgoing crew reported, and the sheet is only as good as the second person who verifies it. Plants that skip the walk keep discovering at 03:00 that the silo is emptier than the page said.

A second shift also doubles the pallet fleet in circulation and doubles the curing places needed, as set out in production planning for a block factory. The handover sheet is where that doubling becomes visible shift by shift, because the yard count is on it every day rather than once a month.

How do the records turn into pay and rotation decisions without gaming?

Pay against reconciled output, never against the counter alone, and never against a single number. A bonus that pays only for blocks invites a crew to run fast and stack soft blocks in the open. A bonus that pays only for rejects invites a crew to stop the line. Pair the two, add unplanned stoppage minutes as a third term with a floor rather than a target, and the incentive lines up with what the plant actually sells.

Rotation needs the same treatment. The night shift carries worse light, colder concrete and less supervision, and a plant that compares shifts on raw output will always find the night shift behind. Compare each shift against its own four week average, and compare products only against the same product. A crew that runs pavers all week will never match a crew that runs hollow blocks, and a supervisor who is punished for that stops recording honestly.

Paper, spreadsheet or dashboard: which one survives a real plant?

Start with paper at the machine and one spreadsheet per month. The sheet is filled where the numbers are produced, the spreadsheet is typed from the sheets by one named person, and the monthly total is reviewed against tonnage bought rather than against the previous month's enthusiasm. Software earns its place when the plant runs two or more lines or more than one site, because then the comparison between lines is the value, not the record itself.

What does not survive is a system that requires the crew to walk to an office to enter data at the end of a shift. The data arrives late, incomplete and rounded. The record has to live within arm's reach of the machine, and the monthly review has to be short enough that the supervisor wants it to be right.

A plant that keeps this sheet for one quarter ends up with something more useful than a report: a baseline. Cement per thousand blocks, pallets broken per thousand, stoppage minutes per thousand, all measured on its own machine with its own crew. That baseline is what makes a quotation for the next line, or a decision to add a second shift, an arithmetic question instead of a guess. Send the model, the products and the shift pattern and the sheet can be set up before the machine lands. Start from the contact page, and for the parts side of the same routine see block plant maintenance and spare parts.

FAQ

Frequently Asked Questions

What should a shift handover record contain in a block plant?
It should carry ten fields on one page: cycles and blocks formed, pallets filled, rejects with reasons, stoppage minutes against fixed cause codes, the mould fitted and its accumulated cycles, cement and aggregate on hand, pressure and oil temperature at handover, open faults and any bypassed sensor, curing yard entries by date, and the physical checks the incoming supervisor must complete before restarting the line.
How do you check whether a shift actually produced what it reported?
Multiply pallets filled by blocks per mould and compare the result with the PLC cycle counter. A QST6-15 forms six hollow blocks per cycle on a 980 x 680 x 20 mm pallet, so roughly one pallet per cycle. A gap between the two counts means pallets were removed for repair, double counted, or the log was filled in from memory at the end of the shift.
Why should stoppage minutes be coded instead of described?
Because a description cannot be added up. Nine fixed codes cover a block plant: no cement or aggregate, no pallets, mould change, mechanical, hydraulic, electrical and control, quality hold, yard or truck full, and power. Each stop gets one code and one number of minutes, so the monthly total shows which cause actually costs the plant hours, and that total is what turns into a work order.
How long should a handover between two shifts take?
About ten minutes at the machine after the sheet is read. The incoming supervisor checks the pressure gauge against the rated pressure of the model, oil level and temperature, the mould fitted and its edge condition, the pallet magazine and yard stack, and the silo level against the tonnage written down. Verbal handovers lose the details that matter at 03:00.
Should a block plant pay a shift bonus on output alone?
No. A bonus paid only for blocks encourages speed and soft stacking, and a bonus paid only for rejects encourages stopping the line. Pair reconciled output with reject share, add unplanned stoppage minutes as a third term with a floor rather than a target, and compare each shift against its own four week average instead of against the other shift.
Does a small block plant need software for shift records?
Not at first. A paper sheet filled at the machine and one monthly spreadsheet typed by a named person is enough for a single line, and it survives a shift that ends at midnight. Software starts to earn its cost when a plant runs two or more lines or more than one site, because then the comparison between lines is the value rather than the record itself.