Customer claims

Rejected Block Delivery: How a Plant Handles a Customer Claim

What to do in the first hour after a rejected block delivery, which six documents decide the claim, and how to settle it without setting a precedent for every later load.

QUICK ANSWER

A rejected block delivery is an evidence problem before it is a price negotiation. The plant should stop the unloading, quarantine the pieces, photograph the load where it sits, and pull the batch record for the day it was formed before anyone offers a replacement. Most claims close on three documents: the signed delivery note, the 7 day compressive result for that batch, and the buyer's own measurement of height and length. Settlement is then a choice between a replacement load, a credit note, or a reduced rate on the quantity delivered. Freight follows fault, and it is settled last.

A rejected block delivery arrives as a conversation between a driver, a site engineer and a phone call to the plant, usually inside an hour of unloading. What decides the outcome is not who is louder. It is whether the plant can produce, that same day, the batch record, the test result and the delivery note that describe the blocks on that truck. This page covers the process between the first call and the closed claim: what counts as a rejection, what to photograph, which documents decide it, how the pieces are counted, which settlement fits, and what has to change afterwards so the same claim does not come back next month. Truck arithmetic and weights are on the weighbridge page, and the contract side is on the supply agreement page.

What makes a block delivery rejected rather than argued about?

A delivery becomes a rejection when the buyer measures, tests or sees something that fails the specification he ordered against. Three families cover almost every real case, and each has a different way of being settled.

  • Dimensional failure. Height, length or width outside the tolerance, measured across a pallet with a steel rule or a caliper. It is objective and it can be settled at the gate.
  • Strength failure. A 7 day or 28 day compressive result below the class named in the order. It cannot be settled at the gate, because the number arrives after the blocks have been laid.
  • Appearance failure. Cracks, chipped corners, crumbling edges and colour banding. This is where most arguments start, because appearance is judged by eye and by the time a buyer complains, the blocks have been handled by his own crew.

Two conditions turn a complaint into a claim the plant has to answer. The blocks must still be identifiable, meaning the delivery note ties them to one truck, one day and one batch. And the failure must be measurable by a method both sides accept. Where a buyer says the blocks are bad without measuring anything, the useful move is not to argue but to supply the measurement: bring a rule, bring the batch result, offer a joint sample.

What should the plant do in the first hour after a rejected block delivery?

The first hour decides whether the claim can be closed on evidence or has to be negotiated on goodwill. Six actions belong in that hour, in this order.

  1. Stop unloading. A load half on the truck and half on the ground can no longer be counted or photographed cleanly, and the buyer will count what suits him.
  2. Quarantine the rejected pieces in one identified bay, physically apart from the buyer's saleable stock.
  3. Photograph five frames: the whole stack, the top layer from above, a close up of the defect, the signed delivery note, and the truck plate.
  4. Write down the batch number and the forming date from the plant record, not from memory and not from the driver's account.
  5. Count accepted and rejected pieces separately and put both numbers on the delivery note before anyone leaves the site.
  6. Promise a response time, not an outcome. A written answer within 48 hours is a promise the plant can keep. A replacement promised on the phone is a decision taken before the evidence exists.

The person who takes that call should be named in advance, and it should not be the driver. A driver who promises a replacement on the plant's behalf creates a claim the plant never agreed to, and in a market where the buyer and the plant will meet again, that promise is remembered longer than the defect.

How do you separate a plant fault from a handling fault?

Most rejected deliveries contain two faults at once: a real defect and a handling problem that made it visible. The symptom tells you which one to look for first.

SymptomUsual causeWhat settles it
Crack through the middle of many pieces of one batchMix too wet, or blocks moved before 2 to 3 days of curingWater setting in the forming record, plus dispatch age from the delivery note
Corners chipped on the outer layer of the stack onlyTransport, strap pressure, forklift forksLoading photographs, pallet edge condition
Height drifting across the whole batchMould wear, or vibration changedFive blocks measured per pallet at the plant, compared with the mould record
Crumbling edges, low 7 day strengthCement content, or cement that was old or dampCement delivery dates and the mix sheet for that batch
White powder on the block faceEfflorescence from cement or water chemistryStrength result. Efflorescence is not a strength failure by itself
Whole load wet and heavy on arrivalOpen transport, or dispatch before the 7 day pointDispatch date against the curing timetable

The curing timetable is the most common explanation in this region, and it is the one a photograph cannot show. Blocks reach roughly 40 to 60 percent of their 28 day strength at 2 to 3 days and 65 to 80 percent at 7 days, which is where shipping normally starts. A load dispatched at day 3 can be sound inside the plant and brittle on the buyer's site. The forming date on the delivery note answers that question in one line, and the curing page explains why the calendar matters more than the cube result taken on the day of dispatch.

Which documents decide a rejected block delivery?

Six documents carry the whole argument. A plant that cannot produce them within a day is negotiating from weakness, whatever the blocks were actually like.

DocumentWhat it proves
Signed delivery note with piece count, truck plate and timeHow many pieces left and how many arrived, and who accepted them
Batch record for that dayCement and aggregate quantities, water, cycle time, mould fitted, operator
7 day and 28 day compressive resultsWhether the batch met the class it was sold as
Sand moisture logWhether the water was corrected after rain, which is the single most common mix variable
Cement delivery dates and silo recordsWhether the cement was old, damp or from a different supplier
Retained sample from the same batchAllows a joint or third party test on material nobody has touched since

The value of the set is in the chain, not in any single page. A test result that cannot be traced back to a cement delivery and a forming shift is a number without a history, and a buyer's engineer will say so. The quality control page describes the checkpoints that generate these records, and raw material storage covers the gate records that start the chain.

How is the quantity of a rejected load counted?

Blocks are sold by the piece and moved by the tonne, so a rejected load has to be counted twice and the two numbers have to agree. A hollow block of 390 x 190 x 190 mm weighs about 15 kg, so a 10 tonne truck carries roughly 660 pieces, and one shift of 8,640 blocks leaves the yard at about 129.6 tonnes.

Weight is a cross check, not a count. Blocks at day 7 still carry water, so the same 660 pieces can weigh a few hundred kilograms more than the book figure, and a buyer who weighs a wet load will report a quantity that looks short. Count the pieces on the truck, weigh only when the count is disputed, and use a 60 tonne weighbridge with 20 kg divisions so that the difference between a dry and a wet piece does not disappear inside the scale's resolution.

Which settlement option fits which claim?

There are five settlements, and the mistake is reaching for the most expensive one first. Each has a condition under which it is the right answer.

SettlementUse it whenWhat the plant must get in writing
Replacement loadThe fault is the plant's and the buyer needs blocks for a live pourReturn of the rejected pieces, date and quantity of the replacement, who pays each movement
Credit note against the next deliveryThe buyer can use the blocks for non structural workPiece count credited, the batch it applies to, expiry of the credit
Price reduction on the delivered quantityThe shortfall is measured and partial, for example a height band slightly under specThe measurement, the reduced rate, and a statement that the claim is closed
Full refund with the load returnedThe batch failed strength and cannot be used anywhere on the projectTest report, return freight responsibility, condition of the blocks on return
Joint or third party laboratoryThe two sides' results disagree, or the claim is largeSampling method, which retained sample, who pays if the result goes against them

A replacement load is the most expensive answer for the plant, because it pays for production twice and freight twice. It is still the right answer when the buyer's site is stopped, since a stopped site costs him more per day than the load is worth and the relationship rarely survives being made to wait. A credit note is cheaper and is usually accepted where the blocks can go into boundary walls, fill or a non structural application.

Who pays the freight when a load goes back?

Freight follows fault, but it is settled last, after the technical question is closed. Two movements and a forklift at each end can cost more than the blocks themselves, and blocks that come back rarely re-enter saleable stock, because a second handling cycle adds chips that were not there before.

Where the fault is disputed, the load stays where it is until the laboratory result arrives. Moving it twice destroys the evidence and doubles the cost of being wrong. Where the plant is clearly at fault and the distance is long, a credit note is often better for both sides than a return, and it should be offered before the buyer asks for it.

How long should a claim stay open?

A claim that stays open for a month costs more in attention than in blocks, and it trains the buyer to escalate. Four deadlines keep it short and keep the plant credible.

DeadlineWhat happens
Within 4 hoursAcknowledged in writing, load quarantined, photographs and batch number on file
Within 48 hoursWritten position: which documents were checked, what the plant accepts and what it disputes
Within 7 daysDimensional and appearance claims settled, since they can be measured now
Within 28 daysStrength claims settled against the 28 day result, with an interim measure if the buyer's site is running

When is a third party laboratory worth calling?

Call one in three situations: the claim covers a large share of the month's output, the buyer's engineer is acting for a project that will order again, or the plant's own result and the buyer's result disagree by more than the tolerance band. Sample from the set retained for that batch, split the sample so both sides hold material, and let both laboratories test the same blocks.

A result that nobody can dispute is cheaper than a discount given twice, and it settles the question for the next delivery as well. The reject rate page covers what to do when the laboratory confirms an internal problem rather than a dispatch problem.

How does a closed claim change production?

Every closed claim gets one cause code and one sentence, and the monthly count by code is the only number that shows whether the problem sits in production or in dispatch. Six codes cover the field: mix, mould, curing age at dispatch, handling inside the yard, transport, and storage at the buyer's site.

The distribution matters more than the total. A plant whose claims cluster under curing age is not making bad blocks, it is shipping them early to protect a delivery promise, and the fix is a dispatch rule rather than a mix change. A plant whose claims cluster under transport has a loading and strapping problem that no amount of quality control will touch. The yard and loading page covers the loading end, and the transport page covers what the haul actually costs.

Which clauses in the supply agreement prevent the next claim?

Five clauses do most of the work, and all five are cheaper to write before the first truck than to argue after the tenth. The block class and the tolerance, written as a number and naming the standard rather than saying that the blocks comply with it. The test method and who pays for it. The window in which visible damage can be claimed, with 24 hours from delivery being a workable rule. The sampling method and the retained samples. And the settlement ladder, so that the first conversation is about which rung applies rather than about whether compensation is due at all.

All five belong in the supply agreement, and the payment side has to be written to match, otherwise a credit note turns into a discount the plant never chose to give. Payment terms covers how the credit is settled against the next invoice.

What should the plant never do during a claim?

  • Never negotiate at the buyer's gate, where the driver, the crew and the weather are all part of the pressure.
  • Never let the driver commit to a replacement, a refund or a free load.
  • Never accept returned blocks into saleable stock. Quarantine them, then decide between crushing, fill and a reduced price for a non structural use.
  • Never offer a discount before the piece count and the measurement exist, because the discount sets the value of every future claim.
  • Never ship the replacement from the same batch without retesting it, since the fastest way to turn one claim into two is to prove the plant did not look.

If you are setting up the acceptance and dispatch side of a new plant, tell us the block class you will sell, the type of buyer and the delivery radius, and we will write the acceptance section into your supply documents and the dispatch rule into your shift sheet. The contact page reaches the team directly.

FAQ

Frequently Asked Questions

Who decides whether a block delivery is rejected?
The buyer rejects, but the specification decides whether the rejection stands. The plant's job is to make the measurement repeatable: the same rule, the same five blocks per pallet, the same test method named in the order. Where both sides measure with the same method, most claims close in a week without a laboratory.
Can a plant refuse to take back a rejected load?
Yes, when the evidence points to handling, transport or storage at the buyer's site rather than to the blocks as formed. The plant still has to answer in writing and show the batch record and the test result for that day. Refusing without evidence damages the relationship and rarely wins the argument.
How quickly must a buyer report a rejected delivery?
Visible damage should be reported within 24 hours of delivery, while the load can still be identified and photographed. Strength claims follow the 28 day test, which can arrive weeks later. Both windows should be written in the supply agreement before the first truck leaves the yard.
Are rejected blocks ever resold?
Rarely as the same product. Blocks that failed strength should not go into structural work, and blocks damaged in handling cannot be sold as first grade. Some plants crush them for fill or sell them at a reduced rate for boundary walls and temporary works, but only after the cause is known.
Does a rejected delivery always mean a bad batch?
No. Two of the most common causes sit outside production: dispatch before the blocks reached 7 days of curing, and handling or transport that cracked pieces which were sound when they left. In both cases the batch record looks correct and the blocks were damaged on the way to the buyer.
What does a rejected delivery cost the plant?
Two freight movements, the lost pieces, the production time of the replacement and the attention of the manager for a week. The larger cost is rarely the load itself. It is the discount the plant is now expected to give on every later delivery, because the first claim set the precedent.